547 N HIGHLAND AVE 90036

Certificate Information: 547 N HIGHLAND AVE 90036

Application / Permit
24047-10000-00466
Plan Check / Job No.
B24LA06238
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMMING POOL : 25'x 12' & SPA : 7' x 7' PER LA STANDARD PLAN 268
Permit Issued
Issued on 8/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/5/2024 NEHEMIAS RAMOS
Corrections Issued 4/5/2024 NEHEMIAS RAMOS
Plan Check Approved 8/22/2024 ZAW HAN
Issued 8/22/2024 APPLICANT
CofO in Progress 8/29/2025 CRAIG VAUGHAN
Permit Finaled 9/2/2025 DEROLD HAUFF
CofO Issued 9/2/2025 DEROLD HAUFF
Permit Finaled 9/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/14/2024 RIDWAN HARDY

Contact Information

Contractor 3m Pools; Lic. No.: 1045078-C53 9290 53RD ST      JURUPA VALLEY, CA 92509
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/19/2024 Approved CRAIG VAUGHAN
Deck 11/20/2024 Approved CRAIG VAUGHAN
Enclosure/Fence 11/20/2024 Corrections Issued CRAIG VAUGHAN
Deck 11/25/2024 Approved CRAIG VAUGHAN
Enclosure/Fence 11/25/2024 Corrections Issued CRAIG VAUGHAN
Deck 11/27/2024 Approved CRAIG VAUGHAN
Enclosure/Fence 11/27/2024 Not Ready for Inspection CRAIG VAUGHAN
Enclosure/Fence 12/4/2024 Approved CRAIG VAUGHAN
Final 12/20/2024 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready CRAIG VAUGHAN
Final 1/24/2025 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved BRIAN SULLIVAN
Equipment Noise Level 1/28/2025 Approved ANDEY CHAPARRO
Final 2/7/2025 Corrections Issued CRAIG VAUGHAN
Final 2/19/2025 Corrections Issued CRAIG VAUGHAN
Final 3/3/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 3/6/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 3/27/2025 Corrections Issued CRAIG VAUGHAN
Final 6/25/2025 Conditional Approval BRENDAN MORELLI
Special/Order Compliance 6/26/2025 Corrections Issued BRENDAN MORELLI
Final 8/28/2025 OK to Issue CofO CRAIG VAUGHAN