1749 S BEDFORD ST 90035

Certificate Information: 1749 S BEDFORD ST 90035

Application / Permit
24047-10000-00461
Plan Check / Job No.
B24LA06207
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL + SPA PER LOS ANGELES STANDARD PLAN 270. AND ENGINEERED WATER FEATURE
Permit Issued
Issued on 9/16/2024
Issuing Office
Metro
Current Status
Issued on 9/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/9/2024 NEHEMIAS RAMOS
Corrections Issued 4/9/2024 NEHEMIAS RAMOS
Building Plans Picked Up 5/15/2024 APPLICANT
Plan Check Approved 9/16/2024 CARLOS MONTES
Issued 9/16/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 9/10/2024 RIDWAN HARDY

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET UNIT 1      LOS ANGELES, CA 90035

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/24/2024 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/25/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 9/25/2024 Approved ARAM AVEDISIAN
Pool Piping 9/25/2024 Approved ARAM AVEDISIAN
Pre-Gunite 9/25/2024 Conditional Approval ARAM AVEDISIAN
Gas Piping or Gas Test 10/25/2024 No Access for Inspection MEL KHACHATOURIAN
Gas Piping or Gas Test 11/19/2024 Not Ready for Inspection MEL KHACHATOURIAN
Gas Piping or Gas Test 11/26/2024 Approved MEL KHACHATOURIAN
Deck 12/13/2024 Approved BOBBY KEY
Enclosure/Fence 12/13/2024 Corrections Issued BOBBY KEY
Grounding or Bonding 12/13/2024 Partial Approval BOBBY KEY
Enclosure/Fence 4/10/2025 Corrections Issued EVAN COOPER
Enclosure/Fence 5/15/2025 Approved EVAN COOPER
Pre-Gunite 5/15/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Approved EVAN COOPER
Pool Equipment Noise Test 5/20/2025 Approved JUAN ESCOTO DELGADO
Final 5/27/2025 Corrections Issued BOBBY KEY
Final 5/29/2025 Corrections Issued ARAM AVEDISIAN