2334 N GLOVER PL 90031

Certificate Information: 2334 N GLOVER PL 90031

Application / Permit
24047-10000-00397
Plan Check / Job No.
B24LA05283
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL (14'-0" X 10'-6") PER LA CITY STANDARD PLAN 268
Permit Issued
Issued on 8/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2024 APPLICANT
Assigned to Plan Check Engineer 3/22/2024 KHUONG TRUONG
Corrections Issued 3/22/2024 KHUONG TRUONG
Applicant returned to address corrections 7/29/2024 ALEXANDER JOO
Applicant returned to address corrections 8/15/2024 ALEXANDER JOO
Plan Check Approved 8/22/2024 NEHEMIAS RAMOS
Issued 8/22/2024 APPLICANT
CofO in Progress 7/21/2025 HAMIK HARTOUNIAN
Permit Finaled 7/22/2025 DEROLD HAUFF
CofO Issued 7/22/2025 DEROLD HAUFF
Permit Finaled 7/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction within easement Cleared 8/20/2024 TINA MIRANDA

Contact Information

Contractor Blueprint General Contractors Inc; Lic. No.: 1121172-B 2800 MADISON AVE APT G-15      FULLERTON, CA 92821
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/19/2024 Approved HAMIK HARTOUNIAN
Grounding or Bonding 11/26/2024 Not Ready for Inspection JOHN QUINTANILLA
Grounding or Bonding 12/2/2024 Approved LUIS CASTRO
Enclosure/Fence 1/31/2025 Corrections Issued JEFFREY MEAD
Enclosure/Fence 2/6/2025 Corrections Issued HAMIK HARTOUNIAN
Enclosure/Fence 2/7/2025 Corrections Issued HAMIK HARTOUNIAN
Enclosure/Fence 2/11/2025 Corrections Issued BRENDAN MORELLI
Enclosure/Fence 2/18/2025 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/9/2025 Approved HAMIK HARTOUNIAN
Final 4/9/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 7/1/2025 No Access for Inspection HAMIK HARTOUNIAN
Final 7/15/2025 OK to Issue CofO HAMIK HARTOUNIAN