624 N HIGHLAND AVE 90036
Certificate Information: 624 N HIGHLAND AVE 90036
- Application / Permit
- 24047-10000-00270
- Plan Check / Job No.
- B24LA03709
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan: New 16' x 26'-6", 5' Deep Swimming Pool with 7' x 7', 3'-6" Deep Spa and Baja per LA City Standard Plan # 268
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | DAVID CASTILLO |
| Corrections Issued | 3/1/2024 | DAVID CASTILLO |
| Plan Check Approved | 7/12/2024 | DAVID CASTILLO |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 10/29/2024 | CRAIG VAUGHAN |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 3/20/2024 | DALIA MOKAYED |
| Construction near power lines | Cleared | 7/8/2024 | RIDWAN HARDY |
Contact Information
| Contractor | J & A Pools Inc; Lic. No.: 1083573-C53 | 12459 MONTAGUE ST PACOIMA, CA 91331 |
| Engineer | Lacher,, Todd Lee; Lic. No.: NA67656 | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Approved | JEFFREY MEAD |
| Gas Piping or Gas Test | 7/23/2024 | Approved | JEFFREY MEAD |
| Rough-Electrical | 7/23/2024 | Approved | JEFFREY MEAD |
| Rough-Plumbing | 7/23/2024 | Approved | JEFFREY MEAD |
| Deputy Shotcrete | 7/25/2024 | Conditional Approval | ROY SPAULDING |
| Grounding or Bonding | 8/12/2024 | Approved | ROY SPAULDING |
| Enclosure/Fence | 9/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 10/8/2024 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 10/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 10/17/2024 | Approved | CRAIG VAUGHAN |
| Final | 10/21/2024 | Corrections Issued | BRENDAN MORELLI |
| Pre-Gunite | 10/21/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Equipment Noise Level | 10/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Equipment Noise Level | 10/24/2024 | Approved | ANDEY CHAPARRO |
| Final | 10/28/2024 | OK to Issue CofO | CRAIG VAUGHAN |