624 N HIGHLAND AVE 90036

Certificate Information: 624 N HIGHLAND AVE 90036

Application / Permit
24047-10000-00270
Plan Check / Job No.
B24LA03709
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Eplan: New 16' x 26'-6", 5' Deep Swimming Pool with 7' x 7', 3'-6" Deep Spa and Baja per LA City Standard Plan # 268
Permit Issued
Issued on 7/18/2024
Issuing Office
Current Status
CofO Issued on 11/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/1/2024 DAVID CASTILLO
Corrections Issued 3/1/2024 DAVID CASTILLO
Plan Check Approved 7/12/2024 DAVID CASTILLO
Issued 7/18/2024 APPLICANT
CofO in Progress 10/29/2024 CRAIG VAUGHAN
Permit Finaled 11/16/2024 DEROLD HAUFF
Permit Finaled 11/16/2024 DEROLD HAUFF
CofO Issued 11/16/2024 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 3/20/2024 DALIA MOKAYED
Construction near power lines Cleared 7/8/2024 RIDWAN HARDY

Contact Information

Contractor J & A Pools Inc; Lic. No.: 1083573-C53 12459 MONTAGUE ST      PACOIMA, CA 91331
Engineer Lacher,, Todd Lee; Lic. No.: NA67656       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2024 Approved JEFFREY MEAD
Gas Piping or Gas Test 7/23/2024 Approved JEFFREY MEAD
Rough-Electrical 7/23/2024 Approved JEFFREY MEAD
Rough-Plumbing 7/23/2024 Approved JEFFREY MEAD
Deputy Shotcrete 7/25/2024 Conditional Approval ROY SPAULDING
Grounding or Bonding 8/12/2024 Approved ROY SPAULDING
Enclosure/Fence 9/30/2024 Corrections Issued CRAIG VAUGHAN
Enclosure/Fence 10/8/2024 Corrections Issued CRAIG VAUGHAN
Enclosure/Fence 10/10/2024 Corrections Issued BRIAN SULLIVAN
Enclosure/Fence 10/17/2024 Approved CRAIG VAUGHAN
Final 10/21/2024 Corrections Issued BRENDAN MORELLI
Pre-Gunite 10/21/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Not Ready BRENDAN MORELLI
Equipment Noise Level 10/23/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 10/23/2024 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved CRAIG VAUGHAN
Equipment Noise Level 10/24/2024 Approved ANDEY CHAPARRO
Final 10/28/2024 OK to Issue CofO CRAIG VAUGHAN