15027 W HESBY ST 91403

Certificate Information: 15027 W HESBY ST 91403

Application / Permit
24047-10000-00258
Plan Check / Job No.
B24LA03539
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New 30' X 20' pool spa and baja shelf, per standard plan #100
Permit Issued
Issued on 3/7/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 2/27/2024 ALEXANDER JOO
Corrections Issued 2/27/2024 ALEXANDER JOO
Plan Check Approved 3/7/2024 ZAW HAN
Issued 3/7/2024 APPLICANT
CofO in Progress 6/11/2025 JACK KARGODORIAN
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/27/2024 OSCAR CASTRO
Construction within easement Cleared 2/27/2024 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/18/2024 Approved JACK KARGODORIAN
Rough-Electrical 11/18/2024 Approved JACK KARGODORIAN
Rough-Plumbing 11/18/2024 Approved JACK KARGODORIAN
Final 2/21/2025 Corrections Issued JACK KARGODORIAN
Pre-Gunite 2/21/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Approved JACK KARGODORIAN
Final 3/19/2025 Not Ready for Inspection MISAEL ESPARZA
Pool Equipment Noise Test 3/20/2025 Approved FELIPE PENICHE
Deck 3/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Other (see comments) 3/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 3/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/24/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deck 3/28/2025 Not Ready for Inspection JACK KARGODORIAN
Enclosure/Fence 3/28/2025 Corrections Issued JACK KARGODORIAN
Grounding or Bonding 3/28/2025 Not Ready for Inspection JACK KARGODORIAN
Enclosure/Fence 5/12/2025 Corrections Issued JACK KARGODORIAN
Grounding or Bonding 5/12/2025 Corrections Issued JACK KARGODORIAN
Grounding or Bonding 5/21/2025 Partial Approval JACK KARGODORIAN
Final 6/10/2025 OK to Issue CofO JACK KARGODORIAN