5036 N WOODLEY AVE 91436
Certificate Information: 5036 N WOODLEY AVE 91436
- Application / Permit
- 24047-10000-00079
- Plan Check / Job No.
- B24LA00279
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan NEW POOL/ SPA
- Permit Issued
- Issued on 5/9/2024
- Issuing Office
- Current Status
- CofO in Progress on 11/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 2/12/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/13/2024 | CHAD DOI |
| Applicant returned to address corrections | 4/16/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/17/2024 | MAHNAZ NOURHASHEMI |
| Issued | 5/9/2024 | APPLICANT |
| CofO in Progress | 11/6/2025 | JEFFREY HARTLINE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/20/2024 | BRENNEN OBETO |
| ZA Case | Cleared | 2/20/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/14/2024 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 8/5/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Inspection | 8/7/2024 | Approved | SEAN WIRCH |
| Grounding or Bonding | 2/3/2025 | Corrections Issued | JOHN COLEMAN |
| Grounding or Bonding | 2/7/2025 | Corrections Issued | THOMAS FINNILA |
| Grounding or Bonding | 2/14/2025 | Approved | MORRIS JACKSON |
| Enclosure/Fence | 5/14/2025 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 5/21/2025 | Corrections Issued | HENRY KIM |
| Enclosure/Fence | 5/27/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Pool Equipment Noise Test | 6/17/2025 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 9/5/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Approved | THOMAS FINNILA |
| Final | 9/5/2025 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 9/5/2025 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | THOMAS FINNILA |
| ELECTRICAL-Final | 9/17/2025 | Approved | THOMAS FINNILA |
| Final | 9/17/2025 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 9/17/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | THOMAS FINNILA |
| Final | 10/14/2025 | Conditional Approval | THOMAS FINNILA |
| Final | 10/22/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 10/27/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 11/5/2025 | Off-Hour Fees Due | |
| Final | 11/6/2025 | OK to Issue CofO | JEFFREY HARTLINE |