2029 S CENTURY PARK EAST ste 2000n 90067
Certificate Information: 2029 S CENTURY PARK EAST ste 2000n 90067
- Application / Permit
- 24041-10000-42087
- Plan Check / Job No.
- E24LA22579
- Group
- Electrical
- Type
- Electrical
- Sub-Type
- Commercial
- Primary Use
- ()
- Work Description
- [E-Plan] T-24 plan check for an Office T.I. Total affected area is 15,916sq,ft new lighting, power, and distribution equipment
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- Permit Finaled on 10/24/2025
Permit Application Status History
| Submitted | 9/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | ANTHONY DANG |
| Corrections Issued | 9/20/2024 | ANTHONY DANG |
| Plan Check Approved | 11/15/2024 | ANTHONY DANG |
| Issued | 11/19/2024 | APPLICANT |
| Permit Finaled | 10/24/2025 | STEVE SMAY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | O'Bryant Electric Inc; Lic. No.: 386619-C10 | 2900 FAIRVIEW PARK DR FALLS CHURCH, VA 22042 |
| Engineer | Wong,, Tik Keong; Lic. No.: E15617 | 6822 VANDERBILT ST CHINO, CA 91770 |
Inspector Information
| GEORGE LELEA, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| GONZALO GARCIA, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| VICTOR PUKHALSKY, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID KOSKI, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAKE MARTINEK, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough | 7/29/2025 | Partial Approval | VICTOR PUKHALSKY |
| Rough | 8/20/2025 | Partial Approval | DAVID KOSKI |
| T-Bar Ceiling | 9/2/2025 | Partial Approval | DAVID KOSKI |
| T-Bar Ceiling | 9/5/2025 | Partial Approval | VICTOR PUKHALSKY |
| T-Bar Ceiling | 9/11/2025 | Partial Inspection | DAVID KOSKI |
| T-Bar Ceiling | 9/16/2025 | Partial Approval | DAVID KOSKI |
| Rough | 9/24/2025 | Approved | DAVID KOSKI |
| T-Bar Ceiling | 9/24/2025 | Approved | DAVID KOSKI |
| Service/Power Release | 10/2/2025 | Approved | DAVID KOSKI |
| Final | 10/15/2025 | Partial Inspection | VICTOR PUKHALSKY |
| Final | 10/24/2025 | Permit Finaled | STEVE SMAY |