227 N BURLINGTON AVE 90026

Certificate Information: 227 N BURLINGTON AVE 90026

Application / Permit
24030-30000-04326
Plan Check / Job No.
B24WL00241
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading for New 3-story Duplex over 1-level basement 4-car garage and attached ADU
Permit Issued
Issued on 4/3/2025
Issuing Office
Metro
Current Status
Permit Finaled on 4/20/2026

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Zoning Architect 2/1/2024 SARHAD GHEVANDIAN
Assigned to Plan Check Engineer 2/15/2024 YASHAR EMAMI
Corrections Issued 2/28/2024 YASHAR EMAMI
Quality Review Completed 3/12/2024 REZA HAGHIGHAT
Building Plans Picked Up 3/18/2024 APPLICANT
Disabled Access Plans Picked Up 3/22/2024 APPLICANT
Applicant returned to address corrections 7/16/2024 YASHAR EMAMI
Applicant returned to address corrections 7/24/2024 YASHAR EMAMI
Plan Check Approved 2/19/2025 YASHAR EMAMI
Issued 4/3/2025 APPLICANT
Permit Finaled 4/20/2026 RAMAZANALI ALMASI

Permit Application Clearance Information

ZA Case Cleared 12/19/2024 RUBEN VASQUEZ
Excavation more than 5-ft deep Cleared 1/29/2025 CALOSHA APPROVED

Contact Information

Architect , ; Lic. No.: C35150       ,
Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/22/2025 Approved RUSSELL BONVOULOIR
Deputy Grading 4/28/2025 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 6/3/2025 Conditional Approval RUSSELL BONVOULOIR
Rough 7/10/2025 No Access for Inspection RUSSELL BONVOULOIR
Fill/Backfill 7/15/2025 Partial Inspection RUSSELL BONVOULOIR
Sub-Drain 7/15/2025 Corrections Issued RUSSELL BONVOULOIR
Fill/Backfill 7/21/2025 Partial Inspection JONATHAN HOM
Sub-Drain 7/21/2025 Corrections Issued JONATHAN HOM
Bottom/Toe 4/9/2026 Approved RAMAZANALI ALMASI
Final 4/9/2026 Corrections Issued RAMAZANALI ALMASI
Rough 4/9/2026 Not Ready for Inspection RAMAZANALI ALMASI
Approved Compaction Report 4/20/2026 Approved RAMAZANALI ALMASI
Final 4/20/2026 Permit Finaled RAMAZANALI ALMASI
Rough 4/20/2026 Approved RAMAZANALI ALMASI