933 S BUNDY DR 90049

Certificate Information: 933 S BUNDY DR 90049

Application / Permit
24030-30000-02550
Plan Check / Job No.
B24WL00902
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
site grading for new SFD and ADU -3 of 3-
Permit Issued
Issued on 1/22/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/22/2025

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/8/2024 KAVIAN REFAHI
Corrections Issued 5/12/2024 KAVIAN REFAHI
Quality Review Completed 5/23/2024 CHIHARU SUZUKI
Building Plans Picked Up 5/24/2024 APPLICANT
Applicant returned to address corrections 5/31/2024 KAVIAN REFAHI
Applicant returned to address corrections 7/2/2024 KAVIAN REFAHI
Applicant returned to address corrections 8/26/2024 KAVIAN REFAHI
Applicant returned to address corrections 9/11/2024 KAVIAN REFAHI
Plan Check Approved 10/21/2024 KAVIAN REFAHI
Issued 1/22/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/4/2024 DARIN LAM
Work Adjacent to Public Way Cleared 9/18/2024 LIAM ODONOVAN
Miscellaneous Cleared 10/21/2024 KAVIAN REFAHI

Contact Information

Contractor Owner-Builder       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Prasad,, Amarendra; Lic. No.: C68517 365 FLOWER LN      MOUNTAIN VIEW, CA 94043
Engineer Salama,, Nader; Lic. No.: C75041 2768 BOLLINGER CANYON ROAD      SAN RAMON, CA 94583

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/18/2025 Approved MATTHEW JENKINS
Excavation 4/2/2025 Partial Approval MATTHEW JENKINS
Initial Grading 4/2/2025 Partial Inspection MATTHEW JENKINS
Bottom/Toe 4/7/2025 Partial Approval MATTHEW JENKINS
Excavation 4/7/2025 Partial Inspection MATTHEW JENKINS
Bottom/Toe 4/10/2025 Partial Approval MATTHEW JENKINS
Deputy Grading 4/10/2025 Conditional Approval MATTHEW JENKINS
Excavation 4/10/2025 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 5/1/2025 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 7/7/2025 Approved MATTHEW JENKINS