336 N RENO ST 90026
Certificate Information: 336 N RENO ST 90026
- Application / Permit
- 24030-30000-01866
- Plan Check / Job No.
- B24WL00679
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Site grading for new retaining wall and R&R for new 3-story duplex and 3-story SFD w./ ADU
- Permit Issued
- Issued on 8/7/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/19/2026
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | REZA HAGHIGHAT |
| Corrections Issued | 4/6/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 4/11/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/11/2024 | APPLICANT |
| Plan Check Approved | 6/20/2024 | REZA HAGHIGHAT |
| Issued | 8/7/2024 | APPLICANT |
| Permit Finaled | 2/19/2026 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 6/20/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/20/2024 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Residential Alchemists; Lic. No.: 1098394-B | 2088 S ATLANTIC BLVD #276 MONTEREY PARK, CA 91754 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
| Engineer | Lee,, Allen; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/8/2024 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 8/20/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 8/22/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 8/26/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 8/30/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 9/9/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 10/28/2024 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 1/2/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Final | 1/2/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Rough | 1/2/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 1/23/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 1/27/2026 | Approved | MICHAEL TEMPLE |
| Bottom/Toe | 2/3/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 2/3/2026 | Corrections Issued | RAMAZANALI ALMASI |
| Rough | 2/3/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 2/10/2026 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 2/11/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 2/11/2026 | Corrections Issued | RAMAZANALI ALMASI |
| Rough | 2/11/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Drainage Devices/Catch Basin | 2/13/2026 | Partial Approval | RAMAZANALI ALMASI |
| Final | 2/13/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Rough | 2/13/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Bottom/Toe | 2/19/2026 | Approved | RAMAZANALI ALMASI |
| Final | 2/19/2026 | Permit Finaled | RAMAZANALI ALMASI |
| Rough | 2/19/2026 | Approved | RAMAZANALI ALMASI |