545 N HANLEY PL 90049
Certificate Information: 545 N HANLEY PL 90049
- Application / Permit
- 24030-20000-08295
- Plan Check / Job No.
- B24VN27184
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR BASEMENT, RETAINING WALL AND POOL/SPA. 4 OF 6
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/30/2025
Permit Application Status History
| Submitted | 12/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | RAPHAEL ROSAS |
| Corrections Issued | 1/6/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 1/6/2025 | STEVEN KIM |
| Building Plans Picked Up | 1/8/2025 | APPLICANT |
| Applicant returned to address corrections | 2/18/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/21/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/28/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/27/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 5/30/2025 | RAPHAEL ROSAS |
| Issued | 5/30/2025 | APPLICANT |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 4/30/2025 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/30/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Geologist | Bovenizer,, Ernest; Lic. No.: EG2515 | 5200 RIVERVIEW ROAD NE ATLANTA, GA 30327 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Approved Compaction Report | 8/15/2025 | Approved | LANNY MERRICK |
| Rough | 9/17/2025 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 9/17/2025 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 10/8/2025 | Not Ready for Inspection | LANNY MERRICK |
| Excavation | 10/22/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation | 10/24/2025 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 11/4/2025 | Partial Inspection | MATTHEW JENKINS |
| Rough | 11/4/2025 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 11/7/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 11/17/2025 | Approved | MATTHEW JENKINS |
| Approved Compaction Report | 12/2/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 12/5/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 1/14/2026 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 1/27/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation | 1/27/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 1/27/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough | 1/27/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 2/20/2026 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |