1033 W 30TH ST 90007

Certificate Information: 1033 W 30TH ST 90007

Application / Permit
24030-20000-06413
Plan Check / Job No.
B24VN18582
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR REMODEL AND ADDITION OF 3-STORY DUPLEX WITH BASEMENT AND ADU AND TEMPORARY SHORING. "Construction shall not commence without CALOSHA permit"
Permit Issued
Issued on 2/27/2025
Issuing Office
Metro
Current Status
Permit Finaled on 10/24/2025

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 ALFRED RAMIREZ
Corrections Issued 10/6/2024 ALFRED RAMIREZ
Quality Review Completed 10/10/2024 STEVEN KIM
Building Plans Picked Up 10/11/2024 APPLICANT
Applicant returned to address corrections 11/20/2024 ALFRED RAMIREZ
Plan Check Approved 2/25/2025 ALFRED RAMIREZ
Issued 2/27/2025 APPLICANT
Permit Finaled 10/23/2025 JONATHAN HOM

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 3/27/2025 Corrections Issued JONATHAN HOM
Excavation 3/27/2025 Not Ready for Inspection JONATHAN HOM
Excavation 3/28/2025 Corrections Issued JONATHAN HOM
Excavation 4/1/2025 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 4/11/2025 Corrections Issued JONATHAN HOM
Excavation 4/11/2025 Partial Inspection JONATHAN HOM
Excavation 4/14/2025 Partial Approval JONATHAN HOM
Bottom/Toe 4/21/2025 Partial Approval RUSSELL BONVOULOIR
Excavation 6/6/2025 Corrections Issued JONATHAN HOM
Sub-Drain 7/17/2025 Corrections Issued JONATHAN HOM
Sub-Drain 7/18/2025 Partial Approval JONATHAN HOM
Approved Compaction Report 10/2/2025 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 10/16/2025 Partial Inspection JONATHAN HOM
Final 10/16/2025 Partial Inspection JONATHAN HOM
Rough 10/16/2025 Partial Inspection JONATHAN HOM
Bottom/Toe 10/23/2025 Approved JONATHAN HOM
Final 10/23/2025 Permit Finaled JONATHAN HOM
Rough 10/23/2025 Approved JONATHAN HOM