11410 W BURBANK BLVD 91601
Certificate Information: 11410 W BURBANK BLVD 91601
- Application / Permit
- 24030-20000-05655
- Plan Check / Job No.
- B24VN15979
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePlan - SITE GRADING FOR PROPOSED 5 STORY APARTMENT, SEE COMMENTS CalOSHA permit must be obtained before construction is commenced
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/29/2025
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | STARR CHEN |
| Corrections Issued | 10/1/2024 | STARR CHEN |
| Quality Review Completed | 10/1/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/31/2024 | STARR CHEN |
| Applicant returned to address corrections | 1/9/2025 | STARR CHEN |
| Plan Check Approved | 4/11/2025 | STARR CHEN |
| Issued | 4/29/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | MARKOS PEREZ-BRAN |
| Work Adjacent to Public Way | Cleared | 1/15/2025 | ALEXANDER PHAM |
| Low Impact Development (LID) | Cleared | 1/27/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/28/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | N P Construction Company; Lic. No.: 977919-B | 9 CUSHING SUITE 200 IRVINE, CA 92618 |
| Engineer | Derkalousdian,, Hrair Harry; Lic. No.: C79694 | 3622 VIRGINIA STREET GLENDALE, CA 91214 |
| Engineer | Luong,, John Tuan; Lic. No.: C65214 | 8171 INGRAM CIR WESTMINSTER, CA 92683 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/21/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/3/2025 | Conditional Approval | ALEXANDER HELFER |
| Excavation | 6/3/2025 | Corrections Issued | ALEXANDER HELFER |
| Deputy Grading | 6/4/2025 | Approved | ALEXANDER HELFER |
| Excavation | 6/4/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/5/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/6/2025 | Approved | ALEXANDER HELFER |
| Excavation | 6/6/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/9/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 6/10/2025 | Approved | ALEXANDER HELFER |
| Excavation | 6/10/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 6/11/2025 | Approved | ALEXANDER HELFER |
| Excavation | 6/11/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 6/13/2025 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 6/17/2025 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 7/9/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 7/9/2025 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 7/9/2025 | Conditional Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 7/10/2025 | Corrections Issued | ALEXANDER HELFER |
| Approved Compaction Report | 7/11/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 7/17/2025 | Partial Approval | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/5/2025 | Partial Approval | ALEXANDER HELFER |