11410 W BURBANK BLVD 91601

Certificate Information: 11410 W BURBANK BLVD 91601

Application / Permit
24030-20000-05655
Plan Check / Job No.
B24VN15979
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan - SITE GRADING FOR PROPOSED 5 STORY APARTMENT, SEE COMMENTS CalOSHA permit must be obtained before construction is commenced
Permit Issued
Issued on 4/29/2025
Issuing Office
Metro
Current Status
Issued on 4/29/2025

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 STARR CHEN
Corrections Issued 10/1/2024 STARR CHEN
Quality Review Completed 10/1/2024 EUGENE BARBEAU
Applicant returned to address corrections 10/31/2024 STARR CHEN
Applicant returned to address corrections 1/9/2025 STARR CHEN
Plan Check Approved 4/11/2025 STARR CHEN
Issued 4/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2024 MARKOS PEREZ-BRAN
Work Adjacent to Public Way Cleared 1/15/2025 ALEXANDER PHAM
Low Impact Development (LID) Cleared 1/27/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 1/28/2025 EDGAR ALCARAZ

Contact Information

Contractor N P Construction Company; Lic. No.: 977919-B 9 CUSHING SUITE 200      IRVINE, CA 92618
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Luong,, John Tuan; Lic. No.: C65214 8171 INGRAM CIR      WESTMINSTER, CA 92683

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/21/2025 Approved ALEXANDER HELFER
Deputy Grading 6/3/2025 Conditional Approval ALEXANDER HELFER
Excavation 6/3/2025 Corrections Issued ALEXANDER HELFER
Deputy Grading 6/4/2025 Approved ALEXANDER HELFER
Excavation 6/4/2025 Approved ALEXANDER HELFER
Deputy Grading 6/5/2025 Approved ALEXANDER HELFER
Deputy Grading 6/6/2025 Approved ALEXANDER HELFER
Excavation 6/6/2025 Approved ALEXANDER HELFER
Deputy Grading 6/9/2025 Conditional Approval ALEXANDER HELFER
Deputy Grading 6/10/2025 Approved ALEXANDER HELFER
Excavation 6/10/2025 Approved ALEXANDER HELFER
Deputy Grading 6/11/2025 Approved ALEXANDER HELFER
Excavation 6/11/2025 Approved ALEXANDER HELFER
Bottom/Toe 6/13/2025 Partial Approval ALEXANDER HELFER
Bottom/Toe 6/17/2025 Approved ALEXANDER HELFER
Approved Compaction Report 7/9/2025 Not Ready for Inspection ALEXANDER HELFER
Drainage Devices/Catch Basin 7/9/2025 Approved ALEXANDER HELFER
Special/Order Compliance 7/9/2025 Conditional Approval CHARLES POWELL
Drainage Devices/Catch Basin 7/10/2025 Corrections Issued ALEXANDER HELFER
Approved Compaction Report 7/11/2025 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 7/17/2025 Partial Approval ALEXANDER HELFER
Drainage Devices/Catch Basin 8/5/2025 Partial Approval ALEXANDER HELFER