1036 N LANARK ST 90041

Certificate Information: 1036 N LANARK ST 90041

Application / Permit
24030-20000-05607
Plan Check / Job No.
B24VN15767
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW SINGLE FAMILY DWELLING WITH A BASEMENT & RETAINING WALLS
Permit Issued
Issued on 4/2/2025
Issuing Office
Valley
Current Status
Permit Finaled on 5/19/2026

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 MARVEL DELACRUZ
Corrections Issued 9/25/2024 MARVEL DELACRUZ
Quality Review Completed 9/30/2024 JASON HEALEY
Building Plans Picked Up 10/16/2024 APPLICANT
Applicant returned to address corrections 3/26/2025 MARVEL DELACRUZ
Plan Check Approved 4/2/2025 MARVEL DELACRUZ
Issued 4/2/2025 APPLICANT
Permit Finaled 5/18/2026 JONATHAN HOM

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Azadi,, Bijan; Lic. No.: C18972 2825 PLAZA DEL AMO # 179      TORRANCE, CA 90503
Contractor Custom Design Construction; Lic. No.: 737436-B 19528 VENTURA BLVD #687      TARZANA, CA 91356
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Smith,, Randall James; Lic. No.: L5189 2935 HENRIETTA AVE      LA CRESCENTA, CA 91214
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/10/2025 Approved RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 6/26/2025 Corrections Issued RAMAZANALI ALMASI
Drainage Devices/Catch Basin 7/1/2025 Not Ready for Inspection RAMAZANALI ALMASI
Sub-Drain 7/2/2025 Approved RAMAZANALI ALMASI
Bottom/Toe 8/18/2025 Partial Approval RAMAZANALI ALMASI
Special/Order Compliance 1/5/2026 Partial Inspection JONATHAN HOM
Special/Order Compliance 1/6/2026 Corrections Issued JONATHAN HOM
Special/Order Compliance 1/7/2026 Corrections Issued JONATHAN HOM
Excavation 3/16/2026 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 3/26/2026 Partial Approval JONATHAN HOM
Sub-Drain 3/26/2026 Partial Approval JONATHAN HOM
Bottom/Toe 4/27/2026 Partial Inspection JONATHAN HOM
Final 4/27/2026 Corrections Issued JONATHAN HOM
Rough 4/27/2026 Partial Inspection JONATHAN HOM
Approved Compaction Report 5/12/2026 Approved JONATHAN HOM
Bottom/Toe 5/18/2026 Approved JONATHAN HOM
Final 5/18/2026 Permit Finaled JONATHAN HOM
Rough 5/18/2026 Approved JONATHAN HOM