6100 N WOODLEY AVE 91436

Certificate Information: 6100 N WOODLEY AVE 91436

Application / Permit
24030-20000-05239
Plan Check / Job No.
B24VN14116
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR STAGING AREA
Permit Issued
Issued on 12/13/2024
Issuing Office
Valley
Current Status
Issued on 12/13/2024

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 RAPHAEL ROSAS
Corrections Issued 9/3/2024 RAPHAEL ROSAS
Quality Review Completed 9/4/2024 STEVEN KIM
Building Plans Picked Up 9/5/2024 APPLICANT
Plan Check Approved 12/13/2024 RAPHAEL ROSAS
Issued 12/13/2024 APPLICANT

Permit Application Clearance Information

Metro Rail approval Cleared 9/9/2024 JENNIFER SU
"Q" conditions Cleared 9/10/2024 BRENNEN OBETO
ZA Case Cleared 9/10/2024 BRENNEN OBETO
ZA Case Cleared 9/10/2024 BRENNEN OBETO
ZI Cleared 9/10/2024 BRENNEN OBETO
City owned building/parcel Cleared 9/12/2024 RAPHAEL ROSAS
ZI Cleared 9/17/2024 BRENNEN OBETO

Contact Information

Contractor Jacobs Project Management Co; Lic. No.: 920855-B 120 S CENTRAL AVE SUITE 350      CLAYTON, MO 63105
Engineer Nguyen,, Gino; Lic. No.: C62140 11638 KIRWIN CIR      FOUNTAIN VALLEY, CA 92708

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 1/23/2025 Approved ROBERT PINA
Deputy Grading 3/6/2025 No Access for Inspection ROBERT PINA
Deputy Grading 3/7/2025 Approved ROBERT PINA
Deputy Grading 3/21/2025 Approved ROBERT PINA
Excavation 3/21/2025 Approved ROBERT PINA
Deputy Grading 3/24/2025 Approved ROBERT PINA
Deputy Grading 3/25/2025 Approved ROBERT PINA
Deputy Grading 3/26/2025 Approved ROBERT PINA
Deputy Grading 3/27/2025 Approved ROBERT PINA
Deputy Grading 3/28/2025 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 4/1/2025 Approved ROBERT PINA
Deputy Grading 4/4/2025 Partial Approval CHARLES POWELL
Deputy Grading 4/8/2025 Approved ROBERT PINA
Approved Compaction Report 4/9/2025 Corrections Issued MANUEL TEJADA
Deputy Grading 4/10/2025 Approved ROBERT PINA
Deputy Grading 4/11/2025 Approved MANUEL TEJADA
Deputy Grading 4/14/2025 Approved ROBERT PINA
Deputy Grading 4/15/2025 Approved ROBERT PINA
Deputy Grading 4/16/2025 Approved ROBERT PINA
Approved Compaction Report 4/17/2025 Approved MANUEL TEJADA
Deputy Grading 4/17/2025 Approved ROBERT PINA
Deputy Grading 4/21/2025 Approved ROBERT PINA
Deputy Grading 4/22/2025 Approved ROBERT PINA
Approved Compaction Report 4/23/2025 Approved ROBERT PINA
Deputy Grading 4/23/2025 Approved ROBERT PINA
Deputy Grading 4/24/2025 Approved ROBERT PINA
Deputy Grading 4/25/2025 Approved ROBERT PINA
Deputy Grading 4/28/2025 Approved MANUEL TEJADA
Deputy Grading 4/29/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 4/29/2025 Approved MANUEL TEJADA
Deputy Grading 4/30/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 4/30/2025 Approved MANUEL TEJADA
Deputy Grading 5/1/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/1/2025 Approved MANUEL TEJADA
Deputy Grading 5/2/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/2/2025 No Access for Inspection MANUEL TEJADA
Deputy Grading 5/5/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/5/2025 No Access for Inspection MANUEL TEJADA
Deputy Grading 5/6/2025 Approved MANUEL TEJADA
Deputy Grading 5/7/2025 Approved MANUEL TEJADA
Deputy Grading 5/8/2025 Approved MANUEL TEJADA
Deputy Grading 5/9/2025 Approved MANUEL TEJADA
Deputy Grading 5/13/2025 Approved MANUEL TEJADA
Deputy Grading 5/14/2025 Approved MANUEL TEJADA
Deputy Grading 5/15/2025 Approved MANUEL TEJADA
Deputy Grading 5/16/2025 Conditional Approval ALEXANDER HELFER
Deputy Grading 5/19/2025 Approved MANUEL TEJADA
Deputy Grading 5/20/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/20/2025 Approved MANUEL TEJADA
Deputy Grading 5/21/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/21/2025 Approved MANUEL TEJADA
Deputy Grading 5/22/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 5/22/2025 Approved MANUEL TEJADA
Deputy Grading 5/23/2025 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/27/2025 Approved MANUEL TEJADA
Deputy Grading 5/29/2025 Approved MANUEL TEJADA
Deputy Grading 5/30/2025 Approved MANUEL TEJADA
Deputy Grading 6/3/2025 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/4/2025 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/5/2025 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/6/2025 Approved ALEXANDER HELFER
Deputy Grading 6/11/2025 Approved MANUEL TEJADA
Deputy Grading 6/12/2025 Partial Approval CHARLES POWELL
Excavation 6/12/2025 Not Ready for Inspection CHARLES POWELL
Deputy Grading 6/13/2025 Approved MANUEL TEJADA
Deputy Grading 6/16/2025 No Access for Inspection MANUEL TEJADA
Initial Grading 6/18/2025 Not Ready for Inspection CHARLES POWELL
Deputy Other (see comments) 6/27/2025 Approved MANUEL TEJADA
Approved Compaction Report 6/30/2025 Corrections Issued MANUEL TEJADA
Deputy Grading 6/30/2025 Approved MANUEL TEJADA
Deputy Grading 7/1/2025 Approved MANUEL TEJADA
Deputy Grading 7/2/2025 Approved MANUEL TEJADA
Deputy Grading 7/3/2025 Approved MANUEL TEJADA
Deputy Grading 7/8/2025 Approved MANUEL TEJADA
Deputy Grading 7/9/2025 Approved MANUEL TEJADA
Deputy Grading 7/10/2025 Approved MANUEL TEJADA
Deputy Grading 7/11/2025 Approved MANUEL TEJADA
Deputy Grading 7/14/2025 Approved MANUEL TEJADA
Deputy Grading 7/15/2025 Approved MANUEL TEJADA
Deputy Grading 7/16/2025 Approved MANUEL TEJADA
Deputy Grading 7/17/2025 Approved MANUEL TEJADA
Special/Order Compliance 7/17/2025 No Access for Inspection ROBERT DAVIS
Deputy Grading 7/18/2025 Approved MANUEL TEJADA
Special/Order Compliance 7/18/2025 Partial Approval ROBERT DAVIS
Deputy Grading 7/22/2025 Approved MANUEL TEJADA
Deputy Grading 7/23/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 7/24/2025 Corrections Issued MANUEL TEJADA
Deputy Other (see comments) 7/29/2025 Conditional Approval ROBERT DAVIS
Deputy Grading 7/30/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 7/30/2025 Conditional Approval ALEXANDER HELFER
Deputy Other (see comments) 7/31/2025 Approved MANUEL TEJADA
Deputy Grading 8/1/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 8/4/2025 No Access for Inspection ROBERT PINA
Deputy Other (see comments) 9/2/2025 Conditional Approval ALEXANDER HELFER
Deputy Other (see comments) 9/3/2025 No Access for Inspection MANUEL TEJADA
Deputy Other (see comments) 9/4/2025 Conditional Approval GERMAN RODRIGUEZ MENDOZA