2420 S CASTLE HEIGHTS AVE 90034

Certificate Information: 2420 S CASTLE HEIGHTS AVE 90034

Application / Permit
24030-20000-03491
Plan Check / Job No.
B24VN08065
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Excavation and backfill for Retaining wall
Permit Issued
Issued on 10/8/2024
Issuing Office
Valley
Current Status
Permit Finaled on 12/29/2025

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 NAREG ATARIAN
Corrections Issued 7/9/2024 NAREG ATARIAN
Quality Review Completed 7/9/2024 OMID HEDAYAT
Building Plans Picked Up 7/10/2024 APPLICANT
Applicant returned to address corrections 8/22/2024 NAREG ATARIAN
Applicant returned to address corrections 9/11/2024 NAREG ATARIAN
Plan Check Approved 10/7/2024 NAREG ATARIAN
Issued 10/8/2024 APPLICANT
Permit Finaled 12/24/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/7/2024 MATTHEW JENKINS

Contact Information

Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B 2817 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 10/10/2024 Corrections Issued MATTHEW JENKINS
Excavation 10/10/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 10/16/2024 Partial Inspection MATTHEW JENKINS
Rough 10/16/2024 Partial Inspection MATTHEW JENKINS
Rough 10/23/2024 Conditional Approval MATTHEW JENKINS
Fill/Backfill 10/26/2024 Partial Approval MATTHEW JENKINS
Excavation 11/2/2024 Off-Hour Fees Due
Bottom/Toe 11/4/2024 Partial Inspection MATTHEW JENKINS
Excavation 11/4/2024 Conditional Approval MATTHEW JENKINS
Rough 11/4/2024 Partial Inspection MATTHEW JENKINS
Rough 11/14/2024 Approved VASIL MIHALEV
Fill/Backfill 12/31/2024 Partial Inspection MATTHEW JENKINS
Sub-Drain 12/31/2024 Partial Approval MATTHEW JENKINS
Approved Compaction Report 7/31/2025 Approved MATTHEW JENKINS
Approved Compaction Report 12/24/2025 Approved JOHNNY MIRANDA
Bottom/Toe 12/24/2025 Approved JOHNNY MIRANDA
Final 12/24/2025 Permit Finaled JOHNNY MIRANDA