2330 E 3RD ST 90033
Certificate Information: 2330 E 3RD ST 90033
- Application / Permit
- 24030-10000-08016
- Plan Check / Job No.
- B24LA36444
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING (REMOVAL/RECOMPACTION) FOR NEW 53 UNITS APARTMENT BUILDING 4 STORIES FULLY SPRINKLERD
- Permit Issued
- Issued on 3/17/2025
- Issuing Office
- Current Status
- Issued on 3/17/2025
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | HERNAN ARREOLA |
| Corrections Issued | 1/8/2025 | HERNAN ARREOLA |
| Quality Review Completed | 1/9/2025 | PETER KIM |
| Applicant returned to address corrections | 2/19/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/26/2025 | HERNAN ARREOLA |
| Plan Check Approved | 3/17/2025 | HERNAN ARREOLA |
| Issued | 3/17/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2025 | DAVID LOPEZ |
| Work Adjacent to Public Way | Cleared | 2/16/2025 | LARRY LEE |
Contact Information
| Contractor | Mid Construction Group; Lic. No.: 1030925-B | , |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 1718 W PARKSIDE AVE BURBANK, CA 91506 |
| Engineer | Yadegari,, Shahriar; Lic. No.: C64591 | 10301 KESWICK AVE LOS ANGELES, CA 90064 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/26/2025 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Rough | 4/21/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 4/21/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/24/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 5/1/2025 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Grading | 5/1/2025 | Conditional Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 5/7/2025 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Grading | 5/15/2025 | No Result Entered | ROBERT HUGHES |
| Rough | 5/16/2025 | Partial Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 5/20/2025 | Corrections Issued | RAMAZANALI ALMASI |
| Deputy Grading | 5/22/2025 | No Result Entered | ROBERT HUGHES |
| Deputy Grading | 5/23/2025 | No Result Entered | ROBERT HUGHES |
| Approved Compaction Report | 6/6/2025 | Approved | ROBERT PINA |
| Rough | 6/10/2025 | Partial Approval | RAMAZANALI ALMASI |
| Sub-Drain | 8/11/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Sub-Drain | 8/14/2025 | Partial Approval | RAMAZANALI ALMASI |