13765 W RAYWOOD DR 90049

Certificate Information: 13765 W RAYWOOD DR 90049

Application / Permit
24030-10000-07574
Plan Check / Job No.
B24LA33767
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
PROPOSED GRADING FOR NEW RETAINING WALL. 2 OF 2
Permit Issued
Issued on 4/24/2025
Issuing Office
Metro
Current Status
Permit Finaled on 1/28/2026

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 MICHAEL LOPEZ
Corrections Issued 12/4/2024 MICHAEL LOPEZ
Quality Review Completed 12/12/2024 KEN GILL
Building Plans Picked Up 12/12/2024 APPLICANT
Plan Check Approved 4/24/2025 MICHAEL LOPEZ
Issued 4/24/2025 APPLICANT
Permit Finaled 1/27/2026 RUSSELL BONVOULOIR

Permit Application Clearance Information

Watercourse Cleared 1/30/2025 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/18/2025 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 4/24/2025 MICHAEL LOPEZ

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Demers,, Joe Alan; Lic. No.: C71535 894 SANTA MARIA CIRCLE      DUARTE, CA 91010
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/21/2025 Partial Approval JOHNNY MIRANDA
Deputy Grading 5/29/2025 Conditional Approval JOHNNY MIRANDA
Bottom/Toe 6/10/2025 Partial Approval JOHNNY MIRANDA
FLOOD-Proofing Certificate 6/13/2025 Approved JOHNNY MIRANDA
Rough 6/13/2025 Partial Approval JOHNNY MIRANDA
Excavation 6/23/2025 Partial Approval JOHNNY MIRANDA
Sub-Drain 6/27/2025 Approved ALEXANDER HELFER
Fill/Backfill 7/3/2025 Corrections Issued JOHNNY MIRANDA
Approved Compaction Report 11/5/2025 Approved MATTHEW JENKINS
Approved Compaction Report 12/9/2025 Approved LANNY MERRICK
Bottom/Toe 1/27/2026 Approved RUSSELL BONVOULOIR
Final 1/27/2026 Permit Finaled RUSSELL BONVOULOIR
Rough 1/27/2026 Approved RUSSELL BONVOULOIR