3941 S BURNSIDE AVE 90008

Certificate Information: 3941 S BURNSIDE AVE 90008

Application / Permit
24030-10000-07563
Plan Check / Job No.
B24LA30165
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EPLAN. GRADING FOR RETAINING WAL "COMPLY WITH DEPARTMENT ORDER effective date 04/17/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
Permit Finaled on 8/22/2025

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 CRYSTEL MAALOUF
Corrections Issued 11/26/2024 CRYSTEL MAALOUF
Quality Review Completed 12/10/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 3/12/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 5/13/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 5/15/2025 CRYSTEL MAALOUF
Plan Check Approved 5/27/2025 CRYSTEL MAALOUF
Issued 5/28/2025 APPLICANT
Permit Finaled 8/21/2025 JONATHAN HOM

Permit Application Clearance Information

GPI Written Notices Cleared 5/15/2025 JONATHAN HOM
Grading Pre-Inspection Cleared 5/15/2025 JONATHAN HOM
Construction near power lines Cleared 5/21/2025 RIDWAN HARDY
Construction within easement Cleared 5/21/2025 RIDWAN HARDY

Contact Information

Contractor Atlas Builders And Development Inc; Lic. No.: 1064138-B       ,
Contractor Atlas Builders; Lic. No.: 1064138-B       ,
Engineer Chen,, Shaofu; Lic. No.: C76834 5589 CARMELLO COURT      RANCHO CUCAMONGA, CA 91739
Engineer Finley,, Lawrence Rufus; Lic. No.: C46606 1178 E 9TH ST      LONG BEACH, CA 90813

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 6/12/2025 Corrections Issued RUSSELL BONVOULOIR
Excavation 6/20/2025 Corrections Issued JONATHAN HOM
Excavation 6/30/2025 Corrections Issued JONATHAN HOM
Sub-Drain 7/14/2025 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 8/5/2025 Corrections Issued JONATHAN HOM
Approved Compaction Report 8/21/2025 Approved JONATHAN HOM
Bottom/Toe 8/21/2025 Approved JONATHAN HOM
Final 8/21/2025 Permit Finaled JONATHAN HOM
Rough 8/21/2025 Approved JONATHAN HOM