1029 W CHILDS WAY 90089

Certificate Information: 1029 W CHILDS WAY 90089

Application / Permit
24030-10000-05616
Plan Check / Job No.
B24VN12198
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
(eplan) EARLY START GRADING PERMIT FOR USC FOOTBALL PERFORMANCE CENTER
Permit Issued
Issued on 10/15/2024
Issuing Office
Current Status
Issued on 10/15/2024

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 YOUNG KIM
Corrections Issued 9/10/2024 YOUNG KIM
Quality Review Completed 9/18/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 10/3/2024 YOUNG KIM
Plan Check Approved 10/11/2024 YOUNG KIM
Issued 10/15/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/20/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 9/20/2024 AMBER CAMPBELL
Sewer availability Cleared 9/20/2024 AMBER CAMPBELL
ZA Case Cleared 9/26/2024 DALIA MOKAYED
Hydrant and Access approval Cleared 9/30/2024 JOHN CONNEALLY
Green Code Cleared 10/2/2024 YOUNG KIM
Low Impact Development (LID) Cleared 10/3/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/3/2024 TREVOR QUAN
Historic Resource Verification Cleared 10/7/2024 YASMINE BASHIRI
Redevelopment Project Area Cleared 10/7/2024 YASMINE BASHIRI
Fire Marshal Fire Life Safety Cleared 10/8/2024 RONILO MULAWIN
CPC Cleared 10/10/2024 MANERI ROMAN
DAS Clearance Cleared 10/10/2024 CAROLYNN NEPOMUCENO
Excavation more than 5-ft deep Cleared 10/10/2024 CALOSHA APPROVED
Specific Plan Cleared 10/10/2024 MANERI ROMAN

Contact Information

Contractor Clark Construction Group California Lp; Lic. No.: 839892-B       ,

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 10/16/2024 Partial Approval JONATHAN HOM
Excavation 10/16/2024 Partial Approval JONATHAN HOM
Initial Grading 10/16/2024 Approved JONATHAN HOM
Bottom/Toe 10/17/2024 Conditional Approval JONATHAN HOM
Excavation 10/17/2024 Partial Inspection JONATHAN HOM
Excavation 10/22/2024 Conditional Approval JONATHAN HOM
Bottom/Toe 10/23/2024 Conditional Approval JONATHAN HOM
Excavation 10/25/2024 Conditional Approval JONATHAN HOM
Excavation 10/28/2024 Conditional Approval JONATHAN HOM
Bottom/Toe 10/31/2024 Conditional Approval JONATHAN HOM
Excavation 10/31/2024 Conditional Approval JONATHAN HOM
Approved Compaction Report 11/12/2024 Approved RUSSELL BONVOULOIR
Sub-Drain 3/5/2025 Conditional Approval JONATHAN HOM
Sub-Drain 3/7/2025 Conditional Approval JONATHAN HOM
Drainage Devices/Catch Basin 5/19/2026 Partial Approval AL GAMBLE