4551 W SUNSET BLVD 90027

Certificate Information: 4551 W SUNSET BLVD 90027

Application / Permit
24030-10000-05545
Plan Check / Job No.
B24LA18950
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
EPLAN. VOLUNTARY SEISMIC RENOVATION OF AN EXISTING CONCRETE GARAGE.
Permit Issued
Issued on 2/21/2025
Issuing Office
Current Status
Permit Finaled on 7/30/2025

Permit Application Status History

Submitted 8/20/2024 APPLICANT
Assigned to Plan Check Engineer 8/21/2024 FARSHAD ALIMOHAMADI
Assigned to Zoning Architect 8/22/2024 BENNY WONG
Corrections Issued 9/5/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 9/10/2024 DANIEL CHAN
Applicant returned to address corrections 10/12/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/22/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/20/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/26/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/27/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/16/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/17/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 1/8/2025 FARSHAD ALIMOHAMADI
No Progress 1/8/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 1/8/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 2/20/2025 FARSHAD ALIMOHAMADI
Issued 2/21/2025 APPLICANT
Permit Finaled 7/30/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

Zoning Plan Check Cleared 12/24/2024 BENNY WONG
Grading Pre-Inspection Cleared 1/8/2025 FARSHAD ALIMOHAMADI

Contact Information

Contractor Dpr Construction A General Partnership; Lic. No.: 1083716-B       ,

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 2/26/2025 Partial Inspection RUSSELL BONVOULOIR
Initial Grading 3/19/2025 Approved RUSSELL BONVOULOIR
Bottom/Toe 4/3/2025 Approved RUSSELL BONVOULOIR
Excavation 6/11/2025 Partial Inspection RUSSELL BONVOULOIR
Final 7/25/2025 Corrections Issued RUSSELL BONVOULOIR
Rough 7/25/2025 Approved RUSSELL BONVOULOIR
Approved Compaction Report 7/30/2025 Approved RUSSELL BONVOULOIR
Final 7/30/2025 Permit Finaled RUSSELL BONVOULOIR