4551 W SUNSET BLVD 90027
Certificate Information: 4551 W SUNSET BLVD 90027
- Application / Permit
- 24030-10000-05545
- Plan Check / Job No.
- B24LA18950
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- EPLAN. VOLUNTARY SEISMIC RENOVATION OF AN EXISTING CONCRETE GARAGE.
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- Current Status
- Permit Finaled on 7/30/2025
Permit Application Status History
| Submitted | 8/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2024 | FARSHAD ALIMOHAMADI |
| Assigned to Zoning Architect | 8/22/2024 | BENNY WONG |
| Corrections Issued | 9/5/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 9/10/2024 | DANIEL CHAN |
| Applicant returned to address corrections | 10/12/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 10/22/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/20/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/26/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/27/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/16/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/17/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/8/2025 | FARSHAD ALIMOHAMADI |
| No Progress | 1/8/2025 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/8/2025 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/20/2025 | FARSHAD ALIMOHAMADI |
| Issued | 2/21/2025 | APPLICANT |
| Permit Finaled | 7/30/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 12/24/2024 | BENNY WONG |
| Grading Pre-Inspection | Cleared | 1/8/2025 | FARSHAD ALIMOHAMADI |
Contact Information
| Contractor | Dpr Construction A General Partnership; Lic. No.: 1083716-B | , |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/26/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Initial Grading | 3/19/2025 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/3/2025 | Approved | RUSSELL BONVOULOIR |
| Excavation | 6/11/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 7/25/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Rough | 7/25/2025 | Approved | RUSSELL BONVOULOIR |
| Approved Compaction Report | 7/30/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 7/30/2025 | Permit Finaled | RUSSELL BONVOULOIR |