11251 S COMPTON AVE 90059

Certificate Information: 11251 S COMPTON AVE 90059

Application / Permit
24030-10000-05522
Plan Check / Job No.
B24LA21055
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading/hardscape/landscape for Central park renovatoin. Cut = 95 C.Y, Fill = 26 C.Y., Export = 69 C.Y
Permit Issued
Issued on 2/21/2025
Issuing Office
Current Status
Permit Finaled on 3/16/2026

Permit Application Status History

Submitted 9/4/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 ARMEN JIVALAGIAN
Assigned to Zoning Architect 9/5/2024 FRANCIS AHN
Corrections Issued 9/10/2024 ARMEN JIVALAGIAN
Quality Review Completed 9/17/2024 PETER KIM
Building Plans Picked Up 9/24/2024 APPLICANT
Plan Check Approved 2/20/2025 ARMEN JIVALAGIAN
Issued 2/21/2025 APPLICANT
Permit Finaled 3/13/2026 AL GAMBLE

Permit Application Clearance Information

Zoning Plan Check Cleared 9/19/2024 FRANCIS AHN
City owned building/parcel Cleared 10/2/2024 HAROOT AVANESIA
Eng Process Fee Ord 176,300 Cleared 10/2/2024 JUSTIN BICOL
City Hist. Cultural Monument Cleared 10/8/2024 LAMBERT GIESSINGER
Historic monument Cleared 10/8/2024 LAMBERT GIESSINGER
Drainage to Storm Drain Cleared 10/17/2024 ALBERT TAM
Miscellaneous Cleared 10/17/2024 ALBERT TAM
Low Impact Development (LID) Cleared 2/7/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 2/7/2025 TREVOR QUAN
DAS Clearance Cleared 2/11/2025 SHINE LIN

Contact Information

Contractor Addison - Miller Inc; Lic. No.: 1001142-B 1100 W TOWN & COUNTRY RD   SUITE 1250    ORANGE, CA 92868

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 2/26/2025 No Access for Inspection JONATHAN HOM
Initial Grading 3/4/2025 Approved LANNY MERRICK
Bottom/Toe 3/21/2025 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 3/21/2025 Conditional Approval JONATHAN HOM
Sub-Drain 4/11/2025 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 4/28/2025 Partial Approval RUSSELL BONVOULOIR
Irrigation/Landscape 6/20/2025 Not Ready for Inspection JONATHAN HOM
Approved Compaction Report 2/18/2026 Partial Inspection AL GAMBLE
Approved Compaction Report 3/13/2026 Approved AL GAMBLE
Bottom/Toe 3/13/2026 Approved AL GAMBLE
Final 3/13/2026 Permit Finaled AL GAMBLE
Rough 3/13/2026 Approved AL GAMBLE