1432 S BEVERLY DR 1-48 90035
Certificate Information: 1432 S BEVERLY DR 1-48 90035
- Application / Permit
- 24030-10000-05049
- Plan Check / Job No.
- B24LA09302
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan - SITE GRADING FOR PROPOSED APARTMENT
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Issued on 8/12/2025
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | VU NGUYEN |
| Assigned to Zoning Architect | 5/23/2024 | MEGAN KOLP |
| Corrections Issued | 5/24/2024 | VU NGUYEN |
| Quality Review Completed | 5/28/2024 | EUGENE BARBEAU |
| Plan Check Approved | 8/8/2025 | STARR CHEN |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 1/8/2025 | LIAM ODONOVAN |
| Address approval | Cleared | 1/9/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | LIAM ODONOVAN |
| Low Impact Development (LID) | Cleared | 1/21/2025 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 2/1/2025 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 2/1/2025 | STARR CHEN |
| "Q" conditions | Cleared | 6/20/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Mbg Construction Inc; Lic. No.: 1098398-B | , |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/15/2025 | Approved | LANNY MERRICK |
| Bottom/Toe | 8/22/2025 | Corrections Issued | AL GAMBLE |
| Fill/Backfill | 9/2/2025 | Partial Inspection | AL GAMBLE |
| Bottom/Toe | 9/4/2025 | Approved | LANNY MERRICK |
| Fill/Backfill | 9/9/2025 | Partial Approval | LANNY MERRICK |
| Final | 9/11/2025 | Not Ready for Inspection | AL GAMBLE |
| Rough | 9/11/2025 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 9/29/2025 | Approved | MATTHEW JENKINS |