3021 N GILROY ST 90039

Certificate Information: 3021 N GILROY ST 90039

Application / Permit
24030-10000-04797
Plan Check / Job No.
B24LA15501
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR RETAINING WALL AND REMOVE AND RECOMPACTION
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
Permit Finaled on 9/17/2025

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 7/31/2024 DANIEL SANJUAN
Corrections Issued 8/1/2024 DANIEL SANJUAN
Applicant returned to address corrections 10/30/2024 DANIEL SANJUAN
Applicant returned to address corrections 1/24/2025 DANIEL SANJUAN
Applicant returned to address corrections 2/11/2025 DANIEL SANJUAN
Plan Check Approved 2/12/2025 DANIEL SANJUAN
Issued 2/12/2025 APPLICANT
Permit Finaled 9/17/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 2/11/2025 LARRY LEE
Eng Process Fee Ord 176,300 Cleared 2/12/2025 AMBER CAMPBELL

Contact Information

Contractor George C Hopkins Construction Co Inc; Lic. No.: 397266-B       ,
Contractor Hopkins George C Construction Co Inc; Lic. No.: 397266-B       ,
Engineer Ghanim,, Husam; Lic. No.: S5689 1594 CASITAS AVENUE      PASADENA, CA 91103

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 2/19/2025 Corrections Issued RUSSELL BONVOULOIR
Deputy Grading 2/24/2025 Conditional Approval LANNY MERRICK
Excavation 2/25/2025 Partial Approval LANNY MERRICK
Bottom/Toe 2/26/2025 Partial Approval LANNY MERRICK
Excavation 2/27/2025 Partial Approval LANNY MERRICK
Bottom/Toe 2/28/2025 Approved LANNY MERRICK
Excavation 3/4/2025 Partial Approval LANNY MERRICK
Rough 3/11/2025 Partial Inspection JONATHAN HOM
Sub-Drain 4/1/2025 Corrections Issued RUSSELL BONVOULOIR
Final 7/22/2025 Not Ready for Inspection RAMAZANALI ALMASI
Rough 7/22/2025 Not Ready for Inspection RAMAZANALI ALMASI
Approved Compaction Report 8/11/2025 Approved RAMAZANALI ALMASI
Final 9/17/2025 Permit Finaled RAMAZANALI ALMASI
Rough 9/17/2025 Approved RAMAZANALI ALMASI