7408 S FIGUEROA ST 90003

Certificate Information: 7408 S FIGUEROA ST 90003

Application / Permit
24030-10000-04718
Plan Check / Job No.
B24LA15903
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading Permit for proposed apartment building. Removal & Recompact 3,497 c.y., Cut = 3,497 c.y. , Fill = 3,497 c.y.
Permit Issued
Issued on 2/26/2025
Issuing Office
Current Status
Issued on 2/26/2025

Permit Application Status History

Submitted 7/31/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 ARMEN JIVALAGIAN
Corrections Issued 8/17/2024 ARMEN JIVALAGIAN
Quality Review Completed 8/19/2024 PETER KIM
Applicant returned to address corrections 9/11/2024 ARMEN JIVALAGIAN
Plan Check Approved 2/26/2025 ARMEN JIVALAGIAN
Issued 2/26/2025 APPLICANT

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 8/27/2024 MANERI ROMAN
Eng Process Fee Ord 176,300 Cleared 8/27/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 8/27/2024 JEANIE LAM
Construction near power lines Cleared 9/5/2024 TINA MIRANDA
Construction within easement Cleared 9/5/2024 TINA MIRANDA
Low Impact Development (LID) Cleared 9/13/2024 MARTIN FRAGOSO
Excavation more than 5-ft deep Cleared 10/16/2024 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 12/11/2024 ALEXANDER PHAM

Contact Information

Contractor Owner-Builder       ,
Engineer Chapman,, Randy; Lic. No.: C69614 1407 SPYGLASS WAY      CAMARILLO, CA 93012
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 2/28/2025 Not Ready for Inspection JONATHAN HOM
Initial Grading 2/28/2025 Corrections Issued JONATHAN HOM
Bottom/Toe 3/4/2025 Partial Inspection LANNY MERRICK
Excavation 3/4/2025 Partial Approval LANNY MERRICK
Initial Grading 3/4/2025 Approved LANNY MERRICK
Fill/Backfill 3/5/2025 Approved JONATHAN HOM
Excavation 3/6/2025 Partial Approval JONATHAN HOM
Bottom/Toe 3/10/2025 Partial Approval LANNY MERRICK
Bottom/Toe 3/13/2025 Partial Approval JONATHAN HOM
Excavation 3/14/2025 Partial Inspection JONATHAN HOM
Approved Compaction Report 4/29/2025 Approved RUSSELL BONVOULOIR
Final 4/29/2025 Partial Inspection RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 5/21/2025 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 5/28/2025 Conditional Approval JONATHAN HOM