445 S LUCAS AVE 90017
Certificate Information: 445 S LUCAS AVE 90017
- Application / Permit
- 24030-10000-04540
- Plan Check / Job No.
- B24LA12445
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- EPLAN. GRADING FOR RETAINING WALL AND UNDERPINNING OF PORCH/DECK
- Permit Issued
- Issued on 2/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/21/2026
Permit Application Status History
| Submitted | 7/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 7/25/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/13/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/24/2024 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/16/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/16/2025 | CRYSTEL MAALOUF |
| No Progress | 1/16/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/31/2025 | CRYSTEL MAALOUF |
| Issued | 2/13/2025 | APPLICANT |
| Permit Finaled | 5/20/2026 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/17/2024 | MARIE PICHAY |
| GPI Written Notices | Cleared | 11/5/2024 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 11/5/2024 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | Bethany Samuel D; Lic. No.: 1089466-B | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 12/16/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Initial Grading | 12/16/2025 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 12/22/2025 | Partial Approval | RAMAZANALI ALMASI |
| Excavation | 12/22/2025 | Partial Approval | RAMAZANALI ALMASI |
| Fill/Backfill | 1/27/2026 | Partial Inspection | MICHAEL TEMPLE |
| Sub-Drain | 1/27/2026 | Approved | MICHAEL TEMPLE |
| Bottom/Toe | 2/13/2026 | Partial Approval | RAMAZANALI ALMASI |
| Excavation | 2/13/2026 | Partial Approval | RAMAZANALI ALMASI |
| Approved Compaction Report | 5/7/2026 | Approved | RAMAZANALI ALMASI |
| Bottom/Toe | 5/20/2026 | Approved | RAMAZANALI ALMASI |
| Final | 5/20/2026 | Permit Finaled | RAMAZANALI ALMASI |
| Rough | 5/20/2026 | Approved | RAMAZANALI ALMASI |