3455 W SLAUSON AVE 90043
Certificate Information: 3455 W SLAUSON AVE 90043
- Application / Permit
- 24030-10000-03850
- Plan Check / Job No.
- B24LA01672
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Site Grading, remove and recompact
- Permit Issued
- Issued on 9/17/2025
- Issuing Office
- Metro
- Current Status
- Issued on 9/17/2025
Permit Application Status History
| Submitted | 1/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | MANUEL MONTUFAR |
| Assigned to Zoning Architect | 2/1/2024 | MEGAN KOLP |
| Corrections Issued | 2/14/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 2/14/2024 | EUGENE BARBEAU |
| Plan Check Approved | 9/8/2025 | VU NGUYEN |
| Issued | 9/17/2025 | APPLICANT |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 6/23/2025 | LARRY LEE |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2025 | CINDY QI |
| Miscellaneous | Cleared | 7/18/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 7/18/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 7/18/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 7/18/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 7/18/2025 | YINGSHI HUANG |
| Specific Plan | Cleared | 7/18/2025 | YINGSHI HUANG |
| Historic Resource Verification | Cleared | 7/25/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 7/25/2025 | YASMINE BASHIRI |
| Low Impact Development (LID) | Cleared | 8/1/2025 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jacoby,, Samuel John; Lic. No.: C74309 | 16842 VON KARMAN AVE STE 150 IRVINE, CA 92606 |
| Engineer | Zen,, Petrina; Lic. No.: GE3217 | 905 PIEDMONT IRVINE, CA 92620 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/24/2025 | Approved | JONATHAN HOM |
| Deputy Grading | 10/23/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 10/24/2025 | Conditional Approval | JONATHAN HOM |
| Deputy Grading | 10/24/2025 | Approved | JONATHAN HOM |
| Initial Grading | 10/24/2025 | Corrections Issued | JONATHAN HOM |
| Deputy Grading | 10/27/2025 | Approved | JONATHAN HOM |
| Deputy Grading | 10/28/2025 | Approved | JONATHAN HOM |
| Deputy Grading | 10/29/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 10/31/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 10/31/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Other (see comments) | 10/31/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 11/3/2025 | Conditional Approval | RAMAZANALI ALMASI |
| Deputy Grading | 11/5/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Other (see comments) | 11/5/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 11/6/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation | 11/12/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 12/8/2025 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 1/14/2026 | Approved | AL GAMBLE |