Initial Grading
|
3/21/2025
|
Approved
|
LANNY MERRICK
|
|
Bottom/Toe
|
3/25/2025
|
Partial Approval
|
MICHAEL TEMPLE
|
|
Bottom/Toe
|
3/27/2025
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Bottom/Toe
|
4/1/2025
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Bottom/Toe
|
4/11/2025
|
Partial Approval
|
JONATHAN HOM
|
|
Deputy Grading
|
4/14/2025
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Approved Compaction Report
|
4/16/2025
|
Approved
|
ALEXANDER HELFER
|
|
Bottom/Toe
|
4/16/2025
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Approved Compaction Report
|
4/24/2025
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Bottom/Toe
|
5/12/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Deputy Grading
|
5/29/2025
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Deputy Grading
|
5/30/2025
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
6/23/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
6/24/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
6/30/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/7/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/9/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
7/9/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/15/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/23/2025
|
Partial Approval
|
JONATHAN HOM
|
|
Drainage Devices/Catch Basin
|
7/25/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/28/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
7/28/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
7/30/2025
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Sub-Drain
|
8/4/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
8/12/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Approved Compaction Report
|
8/13/2025
|
Approved
|
ROBERT PINA
|
|
Drainage Devices/Catch Basin
|
8/19/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Approved Compaction Report
|
8/21/2025
|
Approved
|
ROBERT PINA
|
|
Drainage Devices/Catch Basin
|
8/27/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
9/4/2025
|
Partial Inspection
|
RAMAZANALI ALMASI
|
|
Excavation
|
9/4/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
9/5/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
9/9/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
9/15/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
9/18/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
9/23/2025
|
Conditional Approval
|
JONATHAN HOM
|
|
Special/Order Compliance
|
9/24/2025
|
Corrections Issued
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
9/29/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
9/30/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
10/14/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
10/24/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
10/29/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Sub-Drain
|
10/29/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Approved Compaction Report
|
11/20/2025
|
Approved
|
RAMAZANALI ALMASI
|
|
Approved Compaction Report
|
11/21/2025
|
Approved
|
RAMAZANALI ALMASI
|
|
Drainage Devices/Catch Basin
|
12/5/2025
|
Partial Approval
|
JONATHAN HOM
|
|
Drainage Devices/Catch Basin
|
12/11/2025
|
Partial Approval
|
JONATHAN HOM
|
|
Drainage Devices/Catch Basin
|
12/19/2025
|
Partial Approval
|
JONATHAN HOM
|
|
Drainage Devices/Catch Basin
|
1/20/2026
|
Partial Approval
|
RAMAZANALI ALMASI
|