3333 N PORTOLA AVE 90032
Certificate Information: 3333 N PORTOLA AVE 90032
- Application / Permit
- 24030-10000-02736
- Plan Check / Job No.
- B24LA06110
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan: GRADING FOR NEW 2-STORY DUPLEX, NEW 2-STORY ADUs, NEW RETAINING WALL
- Permit Issued
- Issued on 12/23/2024
- Issuing Office
- Current Status
- Issued on 12/23/2024
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | KHEDER ALRAZAA |
| Corrections Issued | 4/25/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 5/31/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/28/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 12/4/2024 | KHEDER ALRAZAA |
| Issued | 12/23/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/4/2024 | KHEDER ALRAZAA |
Contact Information
| Contractor | Delaware Pacific Builders Inc; Lic. No.: 1121593-B | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Tuchscher,, James; Lic. No.: C77649 | 5318 E 2ND ST., #539 LONG BEACH, CA 90803 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/25/2025 | Corrections Issued | MICHAEL TEMPLE |
| Initial Grading | 4/28/2025 | Partial Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 5/20/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 5/28/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 5/29/2025 | Partial Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 6/4/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 6/5/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 6/23/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 6/26/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 7/2/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Special/Order Compliance | 7/9/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 7/15/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 7/18/2025 | Partial Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 8/4/2025 | Partial Approval | RAMAZANALI ALMASI |
| Excavation | 8/5/2025 | Partial Approval | RAMAZANALI ALMASI |
| Excavation | 8/7/2025 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Grading | 8/8/2025 | Approved | JONATHAN HOM |
| Excavation | 8/11/2025 | Partial Approval | RAMAZANALI ALMASI |
| Bottom/Toe | 8/12/2025 | Partial Approval | RAMAZANALI ALMASI |
| Fill/Backfill | 8/13/2025 | Partial Approval | RAMAZANALI ALMASI |
| Special/Order Compliance | 9/24/2025 | Corrections Issued | RAMAZANALI ALMASI |
| Bottom/Toe | 10/7/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Special/Order Compliance | 10/7/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Approved Compaction Report | 10/8/2025 | Approved | RAMAZANALI ALMASI |
| Sub-Drain | 1/21/2026 | Conditional Approval | ROBERT PINA |
| Approved Compaction Report | 3/16/2026 | Approved | JONATHAN HOM |