405 N WESTLAKE AVE 90026

Certificate Information: 405 N WESTLAKE AVE 90026

Application / Permit
24030-10000-02324
Plan Check / Job No.
B24LA06653
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(70) Grading - Hillside
Work Description
Site Grading, backfill for new retaining walls
Permit Issued
Issued on 5/24/2024
Issuing Office
Current Status
Permit Finaled on 3/27/2026

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 VU NGUYEN
Corrections Issued 4/22/2024 VU NGUYEN
Quality Review Completed 4/23/2024 EUGENE BARBEAU
Applicant returned to address corrections 5/22/2024 VU NGUYEN
Plan Check Approved 5/24/2024 VU NGUYEN
Issued 5/24/2024 APPLICANT
Permit Finaled 3/27/2026 RAMAZANALI ALMASI

Permit Application Clearance Information

CPC Cleared 4/24/2024 MAYELA VILLA

Contact Information

Contractor Alpha Construction Co Inc; Lic. No.: 241368-B 14601 AETNA STREET      VAN NUYS, CA 91411
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Gaprelian,, Armen; Lic. No.: GE2668 1719 BEN LOMOND DR      GLENDALE, CA 91202
Engineer Hall,, Barbara Lee; Lic. No.: C42206 1669 MONTE VISTA ST      PASADENA, CA 91106

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/28/2024 Approved RUSSELL BONVOULOIR
Special/Order Compliance 5/28/2024 Partial Inspection RUSSELL BONVOULOIR
Special/Order Compliance 6/21/2024 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 10/29/2024 Partial Inspection JONATHAN HOM
Sub-Drain 10/29/2024 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 11/5/2025 Partial Approval RUSSELL BONVOULOIR
Irrigation/Landscape 11/5/2025 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 11/21/2025 Conditional Approval RAMAZANALI ALMASI
Fill/Backfill 11/24/2025 Conditional Approval JONATHAN HOM
Drainage Devices/Catch Basin 11/25/2025 Approved ROBERT PINA
Drainage Devices/Catch Basin 12/23/2025 Not Ready for Inspection RAMAZANALI ALMASI
Sub-Drain 12/23/2025 Not Ready for Inspection RAMAZANALI ALMASI
Drainage Devices/Catch Basin 12/30/2025 Not Ready for Inspection RAMAZANALI ALMASI
Drainage Devices/Catch Basin 12/31/2025 Partial Approval RAMAZANALI ALMASI
Irrigation/Landscape 1/13/2026 Not Ready for Inspection RAMAZANALI ALMASI
Drainage Devices/Catch Basin 3/6/2026 Partial Approval RAMAZANALI ALMASI
Bottom/Toe 3/24/2026 Approved RAMAZANALI ALMASI
Final 3/24/2026 Not Ready for Inspection RAMAZANALI ALMASI
Rough 3/24/2026 Approved RAMAZANALI ALMASI
Approved Compaction Report 3/26/2026 Approved RAMAZANALI ALMASI
Final 3/27/2026 Permit Finaled RAMAZANALI ALMASI