2840 E WABASH AVE 90033

Certificate Information: 2840 E WABASH AVE 90033

Application / Permit
24030-10000-02022
Plan Check / Job No.
B24LA06327
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
SITE GRADING REMOVE AND RECOMPACT
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
Issued on 6/28/2024

Permit Application Status History

Submitted 4/9/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 VU NGUYEN
Corrections Issued 4/18/2024 VU NGUYEN
Quality Review Completed 4/22/2024 EUGENE BARBEAU
Applicant returned to address corrections 5/14/2024 VU NGUYEN
Plan Check Approved 5/30/2024 VU NGUYEN
Issued 6/28/2024 APPLICANT

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 5/7/2024 JOSE RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 5/10/2024 AMBER CAMPBELL

Contact Information

Contractor Ad Builders; Lic. No.: 1068899-B       ,
Contractor Allstate Drywall Inc; Lic. No.: 1068899-B       ,
Engineer Perez,, Christian Jose; Lic. No.: C80680 5061 ROCKVALLEY RD      RANCHO PALOS VERDES, CA 90275
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 8/16/2024 Partial Approval LANNY MERRICK
Initial Grading 8/16/2024 Approved LANNY MERRICK
Bottom/Toe 8/22/2024 Partial Approval LANNY MERRICK
Deputy Grading 8/22/2024 Conditional Approval LANNY MERRICK
Bottom/Toe 8/26/2024 Not Ready for Inspection LANNY MERRICK
Fill/Backfill 8/26/2024 Not Ready for Inspection LANNY MERRICK
Fill/Backfill 8/28/2024 Partial Approval LANNY MERRICK
Deputy Grading 8/30/2024 Approved ROBERT HUGHES
Bottom/Toe 9/3/2024 Partial Approval LANNY MERRICK
Excavation 9/3/2024 Approved LANNY MERRICK
Fill/Backfill 9/4/2024 Partial Approval LANNY MERRICK
Deputy Grading 9/5/2024 Conditional Approval LANNY MERRICK
Deputy Grading 9/25/2024 Conditional Approval LANNY MERRICK
Special/Order Compliance 2/26/2025 Approved LANNY MERRICK
Fill/Backfill 7/29/2025 Not Ready for Inspection MICHAEL TEMPLE
Sub-Drain 7/29/2025 Corrections Issued MICHAEL TEMPLE
Fill/Backfill 8/11/2025 Partial Approval RAMAZANALI ALMASI
Sub-Drain 8/11/2025 Partial Approval RAMAZANALI ALMASI