1311 N GLENDALE BLVD 90026

Certificate Information: 1311 N GLENDALE BLVD 90026

Application / Permit
24030-10000-01789
Plan Check / Job No.
B24LA05575
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
eplan The new outdoor area includes new hardscaping, landscaping, lighting, and reconfiguring grading and site drainage. Earthwork work: Cut- 660 cy, Fill- 830 cy, Import- 170 cy 2 OF 2
Permit Issued
Issued on 9/18/2024
Issuing Office
Valley
Current Status
Permit Finaled on 4/9/2025

Permit Application Status History

Submitted 3/28/2024 APPLICANT
Assigned to Zoning Architect 3/28/2024 MICHAEL LOPEZ
Assigned to Plan Check Engineer 3/28/2024 MICHAEL LOPEZ
Corrections Issued 4/15/2024 MICHAEL LOPEZ
Quality Review Completed 4/19/2024 GARO TELMI
Applicant returned to address corrections 6/5/2024 MICHAEL LOPEZ
Applicant returned to address corrections 7/10/2024 MICHAEL LOPEZ
Applicant returned to address corrections 8/5/2024 MICHAEL LOPEZ
Plan Check Approved 9/10/2024 MICHAEL LOPEZ
No Progress 9/11/2024 MICHAEL LOPEZ
Plan Check Approved 9/11/2024 MICHAEL LOPEZ
Issued 9/18/2024 APPLICANT
Permit Finaled 4/8/2025 ALEXANDER HELFER

Permit Application Clearance Information

"Q" conditions Cleared 5/1/2024 SPENCER WEJROWSKI
ZA Case Cleared 5/1/2024 SPENCER WEJROWSKI
ZA Case Cleared 5/1/2024 SPENCER WEJROWSKI
ZA Case Cleared 5/1/2024 SPENCER WEJROWSKI
ZA Case Cleared 5/6/2024 EDWIN CANO
ZA Case Cleared 5/6/2024 EDWIN CANO
Low Impact Development (LID) Cleared 8/15/2024 MARCO SANCHEZ
Grading Pre-Inspection Cleared 9/10/2024 MICHAEL TEMPLE

Contact Information

Architect Wilder,, Arthur J; Lic. No.: NA27915       ,
Contractor R C I Builders Inc; Lic. No.: 835114-B       ,
Contractor Rci Builders Inc; Lic. No.: 835114-B       ,

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 9/19/2024 Approved RUSSELL BONVOULOIR
Bottom/Toe 9/25/2024 Conditional Approval RUSSELL BONVOULOIR
Bottom/Toe 9/30/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Grading 10/15/2024 Conditional Approval RUSSELL BONVOULOIR
Excavation 10/15/2024 Partial Inspection RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 10/29/2024 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 10/30/2024 Corrections Issued RUSSELL BONVOULOIR
Approved Compaction Report 11/1/2024 Approved RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 11/5/2024 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 11/12/2024 Partial Approval LANNY MERRICK
Bottom/Toe 11/20/2024 Not Ready for Inspection RUSSELL BONVOULOIR
Excavation 11/20/2024 Not Ready for Inspection RUSSELL BONVOULOIR
Bottom/Toe 11/25/2024 Approved ALEXANDER HELFER
Excavation 11/25/2024 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 12/10/2024 Partial Approval RUSSELL BONVOULOIR
Excavation 3/20/2025 Partial Inspection RUSSELL BONVOULOIR
Final 4/8/2025 Permit Finaled ALEXANDER HELFER
Rough 4/8/2025 Approved ALEXANDER HELFER