4475 N PETIT AVE 91436
Certificate Information: 4475 N PETIT AVE 91436
- Application / Permit
- 24030-10000-01706
- Plan Check / Job No.
- B24LA05012
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan: GRADING FOR NEW SFD AND RETAINING WALL cut 1167 cy fill 1051 cy import 0 cu export 139 cy (includes 20% bulk)
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/21/2026
Permit Application Status History
| Submitted | 3/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | JAD BASMA |
| Corrections Issued | 3/24/2024 | JAD BASMA |
| Quality Review Completed | 4/5/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/30/2024 | JAD BASMA |
| Plan Check Approved | 12/17/2024 | JAD BASMA |
| Issued | 12/18/2024 | APPLICANT |
| Permit Finaled | 1/20/2026 | MANUEL TEJADA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/4/2024 | JAD BASMA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/13/2025 | Approved | ROBERT PINA |
| Bottom/Toe | 1/24/2025 | Approved | ROBERT PINA |
| Bottom/Toe | 1/31/2025 | Partial Approval | ROBERT PINA |
| Deputy Grading | 2/3/2025 | Approved | ROBERT PINA |
| Deputy Grading | 2/4/2025 | Approved | ROBERT PINA |
| Initial Grading | 2/24/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 2/25/2025 | Approved | ROBERT PINA |
| Approved Compaction Report | 3/4/2025 | Approved | CHARLES POWELL |
| Deputy Other (see comments) | 3/18/2025 | Approved | ROBERT PINA |
| Drainage Devices/Catch Basin | 3/20/2025 | Partial Approval | ROBERT PINA |
| Bottom/Toe | 3/25/2025 | Approved | ROBERT PINA |
| Excavation | 3/27/2025 | Approved | ROBERT PINA |
| Sub-Drain | 4/4/2025 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/9/2025 | Approved | ROBERT PINA |
| Sub-Drain | 4/14/2025 | Partial Approval | MANUEL TEJADA |
| Approved Compaction Report | 7/30/2025 | Approved | MANUEL TEJADA |
| Sub-Drain | 9/8/2025 | Approved | MANUEL TEJADA |
| Final | 10/31/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Rough | 10/31/2025 | Approved | MANUEL TEJADA |
| Final | 1/20/2026 | Permit Finaled | MANUEL TEJADA |