10508 W WILKINS AVE 90024

Certificate Information: 10508 W WILKINS AVE 90024

Application / Permit
24030-10000-01535
Plan Check / Job No.
B24LA04777
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW RETAINING WALL
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
Permit Finaled on 10/8/2025

Permit Application Status History

Submitted 3/14/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 VIVIAN LAO
Corrections Issued 3/27/2024 VIVIAN LAO
Quality Review Completed 3/27/2024 KEN GILL
Building Plans Picked Up 4/1/2024 APPLICANT
Applicant returned to address corrections 4/15/2024 VIVIAN LAO
Plan Check Approved 5/13/2024 VIVIAN LAO
Issued 6/5/2024 APPLICANT
Permit Finaled 10/7/2025 LANNY MERRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/13/2024 VIVIAN LAO

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sub-Drain 7/23/2024 Partial Approval MATTHEW JENKINS
Bottom/Toe 6/30/2025 Not Ready for Inspection LANNY MERRICK
Final 6/30/2025 Not Ready for Inspection LANNY MERRICK
Rough 6/30/2025 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 7/7/2025 Not Ready for Inspection JOHNNY MIRANDA
Final 7/7/2025 Corrections Issued JOHNNY MIRANDA
Rough 7/7/2025 Not Ready for Inspection JOHNNY MIRANDA
Bottom/Toe 8/5/2025 Partial Inspection RUSSELL BONVOULOIR
Final 8/5/2025 Not Ready for Inspection RUSSELL BONVOULOIR
Rough 8/5/2025 Partial Inspection RUSSELL BONVOULOIR
Bottom/Toe 8/14/2025 Partial Inspection AL GAMBLE
Final 8/14/2025 Not Ready for Inspection AL GAMBLE
Rough 8/14/2025 Partial Inspection AL GAMBLE
Bottom/Toe 9/15/2025 Not Ready for Inspection AL GAMBLE
Final 9/15/2025 Not Ready for Inspection AL GAMBLE
Rough 9/15/2025 Not Ready for Inspection AL GAMBLE
Bottom/Toe 10/1/2025 Partial Inspection AL GAMBLE
Final 10/1/2025 Partial Inspection AL GAMBLE
Rough 10/1/2025 Not Ready for Inspection AL GAMBLE
Bottom/Toe 10/7/2025 Approved LANNY MERRICK
Final 10/7/2025 Permit Finaled LANNY MERRICK
Rough 10/7/2025 Approved LANNY MERRICK