932 W 84TH ST 90044

Certificate Information: 932 W 84TH ST 90044

Application / Permit
24030-10000-01423
Plan Check / Job No.
B24LA04435
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
ePLAN. GRADING FOR NEW APARTMENT
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
Issued on 10/17/2024

Permit Application Status History

Submitted 3/14/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 KEVIN MORALES
Corrections Issued 3/29/2024 KEVIN MORALES
Quality Review Completed 4/1/2024 EUGENE BARBEAU
Plan Check Approved 10/11/2024 KEVIN MORALES
Issued 10/17/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/16/2024 AMBER CAMPBELL
Work Adjacent to Public Way Cleared 10/9/2024 LARRY LEE

Contact Information

Contractor Mid Construction Group; Lic. No.: 1030925-B       ,
Engineer Bozorgnia,, Behrouz; Lic. No.: NA79581       ,

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/28/2024 Corrections Issued JONATHAN HOM
Initial Grading 10/30/2024 Corrections Issued JONATHAN HOM
Initial Grading 11/20/2024 Approved JONATHAN HOM
Bottom/Toe 12/6/2024 Partial Approval JONATHAN HOM
Deputy Grading 12/6/2024 Approved JONATHAN HOM
Bottom/Toe 12/9/2024 Partial Approval JONATHAN HOM
Deputy Grading 12/9/2024 Approved JONATHAN HOM
Deputy Grading 12/10/2024 Approved JONATHAN HOM
Rough 12/10/2024 Partial Approval JONATHAN HOM
Bottom/Toe 12/16/2024 Partial Approval JONATHAN HOM
Bottom/Toe 12/17/2024 Partial Approval JONATHAN HOM
Deputy Grading 12/17/2024 Conditional Approval JONATHAN HOM
Rough 12/17/2024 Partial Inspection JONATHAN HOM
Deputy Grading 12/18/2024 Approved JONATHAN HOM
Deputy Grading 12/19/2024 Approved JONATHAN HOM
Bottom/Toe 12/27/2024 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 1/6/2025 Not Ready for Inspection LANNY MERRICK
Final 1/6/2025 Not Ready for Inspection LANNY MERRICK
Rough 1/6/2025 Not Ready for Inspection LANNY MERRICK
Approved Compaction Report 1/16/2025 Approved LANNY MERRICK
Fill/Backfill 1/16/2025 Approved LANNY MERRICK
Bottom/Toe 1/24/2025 Approved JONATHAN HOM
Final 1/24/2025 Partial Inspection JONATHAN HOM
Rough 1/24/2025 Partial Inspection JONATHAN HOM