5028 N LINDLEY AVE 91316

Certificate Information: 5028 N LINDLEY AVE 91316

Application / Permit
24030-10000-01231
Plan Check / Job No.
B24LA03395
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
ePLAN. GRADING FOR ADDITION TO SFD, NEW ADU, NEW POOL/SPA CUT: 74.15 CY FILL 0 CY IMPORT 0 CY EXPORT 74.15 CY
Permit Issued
Issued on 5/28/2024
Issuing Office
Current Status
Permit Finaled on 7/15/2025

Permit Application Status History

Submitted 2/23/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 JAD BASMA
Corrections Issued 3/2/2024 JAD BASMA
Quality Review Completed 3/5/2024 GARO TELMI
Applicant returned to address corrections 5/22/2024 JAD BASMA
Plan Check Approved 5/23/2024 JAD BASMA
Issued 5/28/2024 APPLICANT
Permit Finaled 7/14/2025 MANUEL TEJADA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/23/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 9/13/2024 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Initial Grading 9/13/2024 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 10/2/2024 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 10/9/2024 Approved MANUEL TEJADA
Bottom/Toe 10/9/2024 Corrections Issued MANUEL TEJADA
Bottom/Toe 12/16/2024 Partial Approval ROBERT PINA
Bottom/Toe 6/26/2025 Not Ready for Inspection MANUEL TEJADA
Final 6/26/2025 Corrections Issued MANUEL TEJADA
Rough 6/26/2025 Not Ready for Inspection MANUEL TEJADA
Bottom/Toe 7/14/2025 Approved MANUEL TEJADA
Final 7/14/2025 Permit Finaled MANUEL TEJADA
Rough 7/14/2025 Approved MANUEL TEJADA