2245 S AMHERST AVE 90064
Certificate Information: 2245 S AMHERST AVE 90064
- Application / Permit
- 24030-10000-01106
- Plan Check / Job No.
- B24LA03380
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePLAN. GRADING FOR NEW APARTMENT
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- Issued on 1/28/2025
Permit Application Status History
| Submitted | 2/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | KEVIN MORALES |
| Corrections Issued | 3/11/2024 | KEVIN MORALES |
| Quality Review Completed | 3/12/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/26/2024 | KEVIN MORALES |
| Plan Check Approved | 1/23/2025 | KEVIN MORALES |
| Issued | 1/28/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/13/2024 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Ornelas F Construction Clean Up Inc; Lic. No.: 784289-B | , |
| Contractor | Ornelas F Construction; Lic. No.: 784289-B | , |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 2/11/2025 | Approved | VASIL MIHALEV |
| Initial Grading | 2/11/2025 | Approved | VASIL MIHALEV |
| Excavation | 2/19/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Other (see comments) | 2/20/2025 | Approved | AL GAMBLE |
| Fill/Backfill | 2/20/2025 | Partial Inspection | AL GAMBLE |
| Deputy Other (see comments) | 2/21/2025 | Approved | AL GAMBLE |
| Excavation | 2/21/2025 | Partial Inspection | AL GAMBLE |
| Excavation | 2/24/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Other (see comments) | 2/25/2025 | Approved | AL GAMBLE |
| Fill/Backfill | 2/26/2025 | Partial Approval | AL GAMBLE |
| Rough | 3/4/2025 | Partial Inspection | AL GAMBLE |
| Approved Compaction Report | 3/28/2025 | Approved | LANNY MERRICK |
| Approved Compaction Report | 4/9/2025 | Approved | AL GAMBLE |
| Drainage Devices/Catch Basin | 4/1/2026 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 4/28/2026 | Partial Approval | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 5/26/2026 | Partial Approval | JOHNNY MIRANDA |