1106-1116 S HARBOR BLVD 90731

Certificate Information: 1106-1116 S HARBOR BLVD 90731

Application / Permit
24030-10000-00872
Plan Check / Job No.
B24LA02640
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
EPLAN Site preparation and soft grading for new buildings under 22010-10000-05983 (BLDG 1) and 23010-10000-00119 (BLDG 2). Property located at Port of LA. Existing parking to remain.
Permit Issued
Issued on 4/1/2024
Issuing Office
Current Status
Permit Finaled on 9/17/2025

Permit Application Status History

Submitted 2/15/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 MICHAEL LOPEZ
Corrections Issued 3/1/2024 MICHAEL LOPEZ
Plan Check Approved 4/1/2024 MICHAEL LOPEZ
Issued 4/1/2024 APPLICANT
Permit Finaled 9/16/2025 LANNY MERRICK

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/7/2024 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Curtom-Matt; Lic. No.: 631020-B       ,
Contractor Matt Construction Corporation; Lic. No.: 631020-B       ,
Engineer Haertle,, John Erwin; Lic. No.: GE2352 10744 CHURCHILL PL      TUSTIN, CA 92782
Engineer Powers,, Brian Frederick; Lic. No.: NA75902       ,

Inspector Information

JESUS RODRIGUEZ, (213) 216-1187 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 5/8/2024 Partial Inspection AL GAMBLE
Deputy Grading 5/8/2024 Partial Approval AL GAMBLE
Deputy Grading 5/9/2024 Conditional Approval AL GAMBLE
Deputy Grading 5/10/2024 Approved AL GAMBLE
Bottom/Toe 5/13/2024 Partial Approval AL GAMBLE
Deputy Grading 5/13/2024 Partial Approval AL GAMBLE
Deputy Grading 5/24/2024 No Access for Inspection AL GAMBLE
Deputy Grading 5/28/2024 No Access for Inspection VASIL MIHALEV
Fill/Backfill 5/30/2024 Partial Inspection AL GAMBLE
Deputy Grading 7/18/2024 Approved AL GAMBLE
Bottom/Toe 7/19/2024 Partial Inspection AL GAMBLE
Deputy Grading 7/19/2024 Approved AL GAMBLE
Excavation 7/22/2024 Partial Inspection AL GAMBLE
Deputy Grading 7/23/2024 No Access for Inspection MATTHEW JENKINS
Fill/Backfill 7/23/2024 Not Ready for Inspection MATTHEW JENKINS
Excavation 7/24/2024 Partial Approval MATTHEW JENKINS
Bottom/Toe 7/25/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 8/9/2024 Partial Approval MATTHEW JENKINS
Deputy Grading 8/9/2024 Conditional Approval MATTHEW JENKINS
Rough 9/26/2024 Partial Approval AL GAMBLE
Rough 10/2/2024 Partial Approval AL GAMBLE
Excavation 10/4/2024 Partial Approval AL GAMBLE
Drainage Devices/Catch Basin 1/22/2025 Partial Approval AL GAMBLE
Drainage Devices/Catch Basin 1/29/2025 Partial Approval AL GAMBLE
Bottom/Toe 8/1/2025 Partial Inspection MATTHEW JENKINS
Final 8/1/2025 Corrections Issued MATTHEW JENKINS
Rough 8/1/2025 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 8/22/2025 Approved LANNY MERRICK
Bottom/Toe 9/16/2025 Approved LANNY MERRICK
Final 9/16/2025 Permit Finaled LANNY MERRICK
Rough 9/16/2025 Approved LANNY MERRICK