20531 W CLARK ST 91367
Certificate Information: 20531 W CLARK ST 91367
- Application / Permit
- 24020-30000-01678
- Plan Check / Job No.
- B24WL07352
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- New retaining walls *** 1 of 3 ***
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/27/2025
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | KAVIAN REFAHI |
| Corrections Issued | 10/3/2024 | KAVIAN REFAHI |
| Quality Review Completed | 10/3/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/8/2024 | APPLICANT |
| Applicant returned to address corrections | 1/15/2025 | KAVIAN REFAHI |
| Plan Check Approved | 1/22/2025 | KAVIAN REFAHI |
| Issued | 1/27/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/15/2025 | KAVIAN REFAHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 310 ENCINO, CA 91316 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2025 | Partial Approval | ROBERT PINA |
| Footing/Foundation/Slab | 4/8/2025 | Partial Approval | ROBERT PINA |
| Masonry Wall/Backfill | 4/21/2025 | Partial Approval | ROBERT PINA |
| Deputy Drilled-In Anchors | 4/30/2025 | Approved | MANUEL TEJADA |
| Footing/Foundation/Slab | 5/6/2025 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 5/15/2025 | Partial Approval | MANUEL TEJADA |
| Masonry Wall/Backfill | 6/5/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/20/2025 | Partial Approval | MANUEL TEJADA |
| Special/Order Compliance | 7/9/2025 | Partial Approval | MANUEL TEJADA |