560 N LUCERO AVE 90272

Certificate Information: 560 N LUCERO AVE 90272

Application / Permit
24020-30000-01390
Plan Check / Job No.
B24WL06118
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) retaining wall to raise the grade in the side & rear of the S.F.D. to the same elevation as the proposed raised deck --3 OF 3--
Permit Issued
Issued on 1/23/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/23/2025

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/13/2024 JAHANSHAH POURHASSAN
Corrections Issued 8/13/2024 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/1/2024 JAHANSHAH POURHASSAN
Plan Check Approved 1/22/2025 JAHANSHAH POURHASSAN
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/1/2024 JAHANSHAH POURHASSAN
Coastal Zone Cleared 11/7/2024 DAVID URITA

Contact Information

Contractor Roc Development Inc; Lic. No.: 424580-B 9461 CHARLEVILLE BOULEVARD   SUITE 610    BEVERLY HILLS, CA 90212
Engineer Amoroso,, Gregory; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Pineda,, Salvador Antonio; Lic. No.: S5233 560 W MAIN STREET   SUITE C-328    ALHAMBRA, CA 91801
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/23/2025 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 5/6/2025 Conditional Approval LANNY MERRICK
Deputy Drilled-In Anchors 5/15/2025 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 5/16/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 5/19/2025 Conditional Approval JOHNNY MIRANDA
Reinforced Concrete Frame 5/23/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 6/4/2025 Conditional Approval JOHNNY MIRANDA
Masonry Wall/Backfill 6/27/2025 Approved ALEXANDER HELFER
Deputy Drilled-In Anchors 7/17/2025 Partial Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 7/17/2025 Partial Approval LANNY MERRICK
Footing/Foundation/Slab 7/17/2025 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 7/18/2025 Conditional Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 11/13/2025 Conditional Approval LANNY MERRICK
Deputy Drilled-In Anchors 12/1/2025 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 12/4/2025 Conditional Approval RUSSELL BONVOULOIR