2468 N BANYAN DR 90049
Certificate Information: 2468 N BANYAN DR 90049
- Application / Permit
- 24020-30000-01204
- Plan Check / Job No.
- B24WL01546
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- two new retaining walls on piles *** 3 of 3 ***
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/25/2025
Permit Application Status History
| Submitted | 7/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | ZENA HADDIS |
| Corrections Issued 2 | 8/20/2024 | ZENA HADDIS |
| Submitted for Second Quality Review | 9/13/2024 | KAVIAN REFAHI |
| Quality Review Completed | 9/13/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/13/2024 | APPLICANT |
| Plan Check Approved | 2/18/2025 | ZENA HADDIS |
| Issued | 2/25/2025 | APPLICANT |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 9/19/2024 | NATHAN ROMINE |
| Miscellaneous | Cleared | 9/19/2024 | NATHAN ROMINE |
| Watercourse | Cleared | 9/20/2024 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 2/18/2025 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/18/2025 | ZENA HADDIS |
| Grading Pre-Inspection | Cleared | 2/18/2025 | ZENA HADDIS |
Contact Information
| Contractor | Thousand Oaks Adu Builders; Lic. No.: 1101931-B | 252 TRIANGLE ST THOUSAND OAKS, CA 91360 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/2/2025 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 5/14/2025 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 5/23/2025 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 5/29/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Masonry | 6/3/2025 | Conditional Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 6/3/2025 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/10/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Masonry | 6/16/2025 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Masonry | 6/17/2025 | Conditional Approval | LANNY MERRICK |
| Masonry Wall/Backfill | 6/17/2025 | Not Ready for Inspection | LANNY MERRICK |
| Piling/Pier/Caisson | 6/23/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Masonry | 6/25/2025 | Conditional Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 6/25/2025 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 7/1/2025 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 9/3/2025 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/15/2025 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Masonry | 9/24/2025 | Conditional Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 9/25/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Masonry | 9/26/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Reinf. Masonry | 10/7/2025 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/7/2025 | Partial Approval | JOHNNY MIRANDA |