469 N UPPER MESA ROAD 90402

Certificate Information: 469 N UPPER MESA ROAD 90402

Application / Permit
24020-30000-00552
Plan Check / Job No.
B24WL00743
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18' long exterior concrete wall, 8' tall and 6" thick and foundation repair and replacement in the front of the house. ****1 of 2****
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
Permit Finaled on 5/29/2025

Permit Application Status History

Submitted 4/8/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 JAHANSHAH POURHASSAN
Corrections Issued 4/15/2024 JAHANSHAH POURHASSAN
Building Plans Picked Up 4/15/2024 APPLICANT
Applicant returned to address corrections 7/30/2024 JAHANSHAH POURHASSAN
Plan Check Approved 8/9/2024 JAHANSHAH POURHASSAN
Issued 8/12/2024 APPLICANT
Permit Finaled 5/29/2025 HERBERT GIRON

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 7/30/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 7/30/2024 VASIL MIHALEV
Coastal Zone Cleared 8/6/2024 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 8/7/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/7/2024 HISASHI KOBAYAKAWA

Contact Information

Contractor Titan Contracting Inc; Lic. No.: 1065317-B 13317 VENTURA BLVD   STE F1    SHERMAN OAKS, CA 91423
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Parker,, Andrew; Lic. No.: C73993 27113 SHOREWOOD ROAD      RANCHO PALOS VERDES, CA 90275
Geologist Irvine,, Jon Alan; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2024 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/4/2024 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 9/4/2024 Corrections Issued JESUS RODRIGUEZ
Deputy Reinf. Concrete 9/6/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/12/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 9/16/2024 No Access for Inspection KENNETH NAGLE
Drywall Nailing 4/15/2025 Not Ready for Inspection JOHNNY MIRANDA
Final 4/15/2025 Corrections Issued JOHNNY MIRANDA
Reinforced Concrete Frame 4/15/2025 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 4/15/2025 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 4/15/2025 Partial Inspection JOHNNY MIRANDA
Drywall Nailing 5/20/2025 Approved HERBERT GIRON
Final 5/20/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/20/2025 Approved HERBERT GIRON
Reinforced Concrete Frame 5/20/2025 Approved HERBERT GIRON
Smoke Detectors 5/20/2025 Corrections Issued HERBERT GIRON
Wood Frame 5/20/2025 Approved HERBERT GIRON
Final 5/29/2025 Permit Finaled HERBERT GIRON
Smoke Detectors 5/29/2025 Approved HERBERT GIRON