469 N UPPER MESA ROAD 90402
Certificate Information: 469 N UPPER MESA ROAD 90402
- Application / Permit
- 24020-30000-00552
- Plan Check / Job No.
- B24WL00743
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18' long exterior concrete wall, 8' tall and 6" thick and foundation repair and replacement in the front of the house. ****1 of 2****
- Permit Issued
- Issued on 8/12/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/29/2025
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2024 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/15/2024 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 4/15/2024 | APPLICANT |
| Applicant returned to address corrections | 7/30/2024 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 8/9/2024 | JAHANSHAH POURHASSAN |
| Issued | 8/12/2024 | APPLICANT |
| Permit Finaled | 5/29/2025 | HERBERT GIRON |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 7/30/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 7/30/2024 | VASIL MIHALEV |
| Coastal Zone | Cleared | 8/6/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 8/7/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Titan Contracting Inc; Lic. No.: 1065317-B | 13317 VENTURA BLVD STE F1 SHERMAN OAKS, CA 91423 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Parker,, Andrew; Lic. No.: C73993 | 27113 SHOREWOOD ROAD RANCHO PALOS VERDES, CA 90275 |
| Geologist | Irvine,, Jon Alan; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2024 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 9/6/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/12/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 9/16/2024 | No Access for Inspection | KENNETH NAGLE |
| Drywall Nailing | 4/15/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 4/15/2025 | Corrections Issued | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 4/15/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Smoke Detectors | 4/15/2025 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 4/15/2025 | Partial Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 5/20/2025 | Approved | HERBERT GIRON |
| Final | 5/20/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/20/2025 | Approved | HERBERT GIRON |
| Reinforced Concrete Frame | 5/20/2025 | Approved | HERBERT GIRON |
| Smoke Detectors | 5/20/2025 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 5/20/2025 | Approved | HERBERT GIRON |
| Final | 5/29/2025 | Permit Finaled | HERBERT GIRON |
| Smoke Detectors | 5/29/2025 | Approved | HERBERT GIRON |