13258 W CHALON ROAD 90049
Certificate Information: 13258 W CHALON ROAD 90049
- Application / Permit
- 24020-30000-00110
- Plan Check / Job No.
- B24WL00174
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW DETACHED RAISED DECK WITH GRADE BEAM
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/27/2024
Permit Application Status History
| Submitted | 1/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | SERGIO SILVA |
| Corrections Issued | 1/31/2024 | SERGIO SILVA |
| Quality Review Completed | 2/6/2024 | KAVIAN REFAHI |
| Plan Check Approved | 4/10/2024 | SERGIO SILVA |
| Issued | 4/11/2024 | APPLICANT |
| Building Plans Picked Up | 4/15/2024 | APPLICANT |
| Permit Finaled | 9/24/2024 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 4/3/2024 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 4/10/2024 | SERGIO SILVA |
| Miscellaneous | Cleared | 4/10/2024 | SERGIO SILVA |
Contact Information
| Architect | Radziner,, Ronald Mark; Lic. No.: C22228 | MARMOL RADZINER & ASSOCIATES 12210 NEBRASKA AVE LOS ANGELES, CA 90025 |
| Contractor | Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B | 12210 NEBRASKA AVENUE LOS ANGELES, CA 90025 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Guzman,, Martin; Lic. No.: C79193 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/24/2024 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2024 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 5/24/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 5/31/2024 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/8/2024 | Approved | KEVIN SARGSYAN |
| Wood Frame | 7/23/2024 | Approved | KEVIN SARGSYAN |
| Final | 9/24/2024 | Permit Finaled | KEVIN SARGSYAN |