4313 N CEZANNE AVE 91364

Certificate Information: 4313 N CEZANNE AVE 91364

Application / Permit
24020-20000-02135
Plan Check / Job No.
B24VN23638
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 5'-0" HIGH RETAINING WALL
Permit Issued
Issued on 1/31/2025
Issuing Office
Valley
Current Status
Permit Finaled on 3/24/2025

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 PETER MOSESIAN
Corrections Issued 11/30/2024 PETER MOSESIAN
Quality Review Completed 12/3/2024 OMID HEDAYAT
Building Plans Picked Up 12/5/2024 APPLICANT
Plan Check Approved 1/31/2025 SEAN SHAHMIRI
Issued 1/31/2025 APPLICANT
Permit Finaled 3/24/2025 ROBERT PINA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/18/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/19/2024 EDGAR ALCARAZ
ZA Case Cleared 12/26/2024 DORIAN AGUILAR
ZA Case Cleared 12/26/2024 DORIAN AGUILAR
ZA Case Cleared 12/26/2024 DORIAN AGUILAR
Specific Plan Cleared 1/27/2025 TIFFANY CORRALES
Grading Pre-Inspection Cleared 1/31/2025 PETER MOSESIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2025 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 2/27/2025 Not Ready for Inspection ROBERT PINA
Excavation/Setback/Form/Re-Bar 2/28/2025 Approved ROBERT PINA
Footing/Foundation/Slab 2/28/2025 Approved ROBERT PINA
Masonry Wall/Backfill 3/4/2025 Not Ready for Inspection ROBERT PINA
Masonry Wall/Backfill 3/6/2025 Partial Approval ROBERT PINA
Masonry Wall/Backfill 3/17/2025 Approved ROBERT PINA
Final 3/24/2025 Permit Finaled ROBERT PINA