1736 N MANDEVILLE LANE 90049

Certificate Information: 1736 N MANDEVILLE LANE 90049

Application / Permit
24020-20000-01581
Plan Check / Job No.
B24VN15963
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(2) NEW 10'-0" HIGH, 609'-0" LONG RETAINING WALL ON PILES
Permit Issued
Issued on 1/3/2025
Issuing Office
Valley
Current Status
Issued on 1/3/2025

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 PETER MOSESIAN
Corrections Issued 9/15/2024 PETER MOSESIAN
Quality Review Completed 10/3/2024 RARES BODEA
Building Plans Picked Up 10/7/2024 APPLICANT
Plan Check Approved 12/23/2024 PETER MOSESIAN
Issued 1/3/2025 APPLICANT

Permit Application Clearance Information

Watercourse Cleared 10/18/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/20/2024 KIMBERLY HERNANDEZ
Landscape for retaining wall Cleared 12/10/2024 ROSALINDA MEZA
Roof/Waste drainage to street Cleared 12/10/2024 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2025 Partial Approval MATTHEW JENKINS
Deputy Reinf. Concrete 4/18/2025 Conditional Approval MATTHEW JENKINS
Piling/Pier/Caisson 4/18/2025 Not Ready for Inspection JOHNNY MIRANDA
Deputy Reinf. Concrete 4/21/2025 Conditional Approval MATTHEW JENKINS
Deputy Other (see comments) 4/24/2025 Conditional Approval JOHNNY MIRANDA
Piling/Pier/Caisson 4/24/2025 Corrections Issued JOHNNY MIRANDA
Deputy Other (see comments) 4/25/2025 Conditional Approval JOHNNY MIRANDA
Piling/Pier/Caisson 4/25/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 5/5/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 5/28/2025 Conditional Approval JOHNNY MIRANDA
Piling/Pier/Caisson 5/28/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 5/29/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Masonry 6/2/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 6/25/2025 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 6/26/2025 Conditional Approval JOHNNY MIRANDA
Deputy Shotcrete 6/26/2025 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 6/26/2025 Partial Approval JOHNNY MIRANDA
Deputy Shotcrete 6/27/2025 Conditional Approval ALEXANDER HELFER