12722 W CUMPSTON ST 91607
Certificate Information: 12722 W CUMPSTON ST 91607
- Application / Permit
- 24020-20000-01200
- Plan Check / Job No.
- B24VN08990
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR NEW SINGLE FAMILY DWELLING WITH BASEMENT.
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- Issued on 7/31/2025
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | PETER MOSESIAN |
| Corrections Issued | 7/18/2024 | PETER MOSESIAN |
| Quality Review Completed | 7/23/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/26/2024 | APPLICANT |
| Applicant returned to address corrections | 2/12/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 5/9/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 6/4/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 6/30/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 7/30/2025 | VAHAN JIVALAGIAN |
| Issued | 7/31/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/23/2024 | JOANNA MARROQUIN |
| ZA Case | Cleared | 12/23/2024 | JOANNA MARROQUIN |
| ZA Case | Cleared | 12/23/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 12/23/2024 | JOANNA MARROQUIN |
Contact Information
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 5979 W 3RD ST SUITE #203 LOS ANGELES, CA 90036 |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Engineer | Zlotnik,, Alexander; Lic. No.: C69417 | 11323 PASEO LA CUMBRE PORTER RANCH, CA 91326 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/6/2025 | Partial Inspection | ALEXANDER HELFER |
| Deputy Grading | 8/7/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Grading | 8/8/2025 | Approved | MANUEL TEJADA |
| Deputy Grading | 8/11/2025 | Approved | ALEXANDER HELFER |
| Deputy Grading | 8/12/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Grading | 8/13/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 8/21/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Piling/Pier/Caisson | 8/22/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Grading | 9/25/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 9/29/2025 | Partial Approval | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 12/9/2025 | Approved | WAYNE REGESTER |
| Deputy Reinf. Concrete | 12/10/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 2/11/2026 | Conditional Approval | RAUL OLAGI |
| Deputy Reinf. Concrete | 2/23/2026 | Conditional Approval | RAUL OLAGI |
| Deputy Reinf. Concrete | 4/13/2026 | Conditional Approval | RAUL OLAGI |
| Deputy Reinf. Concrete | 4/16/2026 | Conditional Approval | RAUL OLAGI |