18473 W DEVONSHIRE ST 91325
Certificate Information: 18473 W DEVONSHIRE ST 91325
- Application / Permit
- 24020-20000-00873
- Plan Check / Job No.
- B24VN07407
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- **ePlan** Construction of a new Verizon cell site with a 50' monopine tree with equipment cabinets located at the base on a concrete pad
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- Permit Finaled on 6/10/2025
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Zoning Architect | 6/13/2024 | LY CHEA |
| Assigned to Plan Check Engineer | 6/20/2024 | REZA HAGHIGHAT |
| Corrections Issued | 6/23/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 7/8/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/27/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/19/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 1/7/2025 | REZA HAGHIGHAT |
| Issued | 1/22/2025 | APPLICANT |
| Permit Finaled | 6/9/2025 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/12/2024 | LESLIE PEREZ |
| Miscellaneous | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 12/12/2024 | LESLIE PEREZ |
| ZI | Cleared | 12/12/2024 | LESLIE PEREZ |
| Zoning Plan Check | Cleared | 1/7/2025 | Samuel Gonzalez |
Contact Information
| Architect | Fulsang,, Eric John; Lic. No.: NA30715 | , |
| Contractor | Metricom Networks; Lic. No.: 1061012-B | , |
| Engineer | Poole,, Richard John; Lic. No.: NA71869 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/5/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Piling/Pier/Caisson | 3/6/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 3/7/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/17/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 5/23/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 6/9/2025 | Permit Finaled | DEANDRE HOFFMAN |