2621 S NEVIN AVE 90011
Certificate Information: 2621 S NEVIN AVE 90011
- Application / Permit
- 24020-20000-00532
- Plan Check / Job No.
- B24VN04498
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Recreational Vehicle Storage
- Work Description
- **EMERGENCY USE OF VIABLE CITY-OWNED PROPERTY (ED3)** USE OF LAND FOR TEMPORARY STORAGE OF OPERABLE AND IN-OPERABLE AUTOMOBILES, RECREATIONAL VEHICLES AND RELATED EQUIPMENT.** Site improvements including new fences, gates, paving, parking lot striping and new driveway entrances.
- Permit Issued
- Issued on 7/23/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 1/21/2025
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | MANUEL MONTUFAR |
| Corrections Issued | 4/8/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 4/8/2024 | EUGENE BARBEAU |
| Plan Check Approved | 4/18/2024 | MANUEL MONTUFAR |
| Issued | 7/23/2024 | APPLICANT |
| Permit Finaled | 1/21/2025 | JOEY BUCHANAN |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 4/9/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 4/10/2024 | ELIZABETH GALLARDO |
| Address approval | Cleared | 4/15/2024 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | AMBER CAMPBELL |
| Hydrant and Access approval | Cleared | 4/18/2024 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 4/18/2024 | ORVAL HERNANDEZ-MARCI |
| Permit | Cleared | 4/18/2024 | ARMEN SARKISIAN |
| Roof/Waste drainage to street | Cleared | 4/18/2024 | ARMEN SARKISIAN |
| Trees in Parkway | Cleared | 4/18/2024 | ADALBERTO VERA |
Contact Information
| Architect | Eckerman,, Brent Robert; Lic. No.: NA19696 | , |
| Contractor | Owner-Builder | , |
| Engineer | Saoud,, Tarik; Lic. No.: C81282 | 616 N SWEETZER AVE #205 LOS ANGELES, CA 90048 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 7/23/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 1/21/2025 | Permit Finaled | JOEY BUCHANAN |