3307 N BLAIR DR 90068

Certificate Information: 3307 N BLAIR DR 90068

Application / Permit
24020-20000-00423
Plan Check / Job No.
B24VN03521
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
Two New Retaining Walls per Engineering. Max 10' Height.
Permit Issued
Issued on 11/13/2024
Issuing Office
Current Status
Issued on 11/13/2024

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 VAHAN JIVALAGIAN
Corrections Issued 3/24/2024 VAHAN JIVALAGIAN
Quality Review Completed 3/27/2024 OMID HEDAYAT
Building Plans Picked Up 4/10/2024 APPLICANT
Applicant returned to address corrections 4/30/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/9/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/31/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/4/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/13/2024 VAHAN JIVALAGIAN
Issued 11/13/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/9/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/7/2025 Corrections Issued ROBERT PINA
Piling/Pier/Caisson 5/9/2025 Approved ROBERT PINA
Deputy Other (see comments) 6/5/2025 Approved ROBERT PINA
Piling/Pier/Caisson 6/5/2025 Corrections Issued ROBERT PINA
Piling/Pier/Caisson 6/10/2025 Partial Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 6/12/2025 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 6/13/2025 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 7/17/2025 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/17/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 7/21/2025 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 8/14/2025 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 10/8/2025 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 10/10/2025 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/22/2025 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 10/23/2025 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 1/20/2026 Approved ROBERT PINA
Footing/Foundation/Slab 1/30/2026 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 2/6/2026 Approved ROBERT PINA
Special/Order Compliance 3/12/2026 Partial Approval ROBERT PINA