8582 N TELFAIR AVE 91352
Certificate Information: 8582 N TELFAIR AVE 91352
- Application / Permit
- 24020-20000-00264
- Plan Check / Job No.
- B24VN02041
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 6' HIGH MASONRY BLOCK WALL ON TOP OF A 2' RETAINING WALL.
- Permit Issued
- Issued on 3/4/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 11/12/2024
Permit Application Status History
| Submitted | 2/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 2/15/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/28/2024 | SERGIO MUNIZ |
| Issued | 3/4/2024 | APPLICANT |
| Permit Finaled | 11/8/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/26/2024 | NATHAN ROMINE |
Contact Information
| Contractor | Savs Enterprises; Lic. No.: 814956-B | 4500 SUNNYCREST DRIVE LOS ANGELES, CA 90065 |
| Engineer | Keshishian,, Nejdeh Erik; Lic. No.: C38341 | 2654 RISA DR GLENDALE, CA 91208 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/13/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/15/2024 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 3/27/2024 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 9/27/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 9/27/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 9/27/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 11/8/2024 | Permit Finaled | DANNY RODRIGUEZ |